Friday, December 16, 2016

12-16-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM cloudy light snow   PM partly cloudy  
Hi 18 Lo 2

No work preformed today due to the weather wind chill below zero

Thursday, December 15, 2016

12-15-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM cloudy light snow   PM partly cloudy  
Hi 8 Lo -2

No work preformed today due to the weather wind chill below zero

Wednesday, December 14, 2016

12-14-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Mostly Sunny   PM Mostly Sunny  
Hi 18 Lo 2

No work preformed today due to the weather wind chill below zero

Tuesday, December 13, 2016

12-13-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Cloudy snow   PM Cloudy  
Hi 26 Lo 15

No work preformed today due to the weather 

Monday, December 12, 2016

12-12-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Cloudy   PM Cloudy  
Hi 31 Lo 15

No work preformed today due to weather.

Friday, December 9, 2016

12-9-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Cloudy Snow  PM cloudy Snow Windy 
Hi 25 Lo 15

No work preformed today due to weather 

Thursday, December 8, 2016

12-8-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Cloudy Snow  PM cloudy Snow Windy 
Hi 28 Lo 15

No work preformed today due to weather 

Wednesday, December 7, 2016

12-7-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Partly Cloudy  PM cloudy
Hi 37 Lo 27

A prefinal inspection was held at 1:00 PM  

Chippewa Punch List
                                                Chippewa Roundabout
1.       Paint Conduit sticking up for Cavalry Temple old sign Electric
2.       Grates fins facing right direction Several
3.       Plastic on ramp Tiles
4.       Route and seal cracks on all new concrete curb and concrete in cavalry temple lot next to curb
5.       Trees Leaning on Chippewa North Side between main and Michigan
6.       Temp tape (trash) on Main/Chippewa island
7.       Remove  ramp and replace with curb and sidewalk on south side of Chippewa between Main and Michigan
8.       Add 2 more sets of round about arrows south on Michigan
9.       Get extra signs up on cable span for round about calling out Main and Michigan.
10.   Get geotextile off of drains south west corner Mich and Chippewa
11.   Add ground Mounted signs for Michigan and Main south of Roundabout
12.   Put up sign by mail box that was stolen R8-3(mod)
13.   Cover for irrigate back flow preventer
14.   Irrigation lines lower below curb on west side
15.   Irrigation wiring on east side
16.   Couple of parking stalls need lines finished  

Donmoyer and Michigan
1.       Tape on signal pole foundation nuts from painting remove
2.       Plastic on crosswalk tile remove
3.       Covers on traffic signal poles

Ewing and Michigan
1.       Concrete sidewalk at Tesco
2.       Tape on signal pole foundation nuts from painting remove
3.       Change out 3m head

Ewing and Main
1.       Concrete around the walk/wait on the North East corner
2.       Change out the 3m heads

3.       West of main Right arrow turn to right/straight

Tuesday, December 6, 2016

12-6-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Cloudy  PM cloudy  


HI 40 LO 32

Martell worked on the intersection on Michigan and Ewing replacing the Cabinet and controller. They also worked on the intersection of Main and Ewing.

Reith Riley poured the colored concrete island back at the intersection of Chippewa and Main. 

no other work took place today.

12-5-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Cloudy  PM cloudy   


HI 38 LO 31

Martell worked on replacing the cabinets and controllers at the intersection of Donmoyer and Michigan. They also worked on the Intersection of Ewing and Michigan.

No other work took place today.

Friday, December 2, 2016

12-2-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Cloudy drizzle PM cloudy drizzle  
HI 38 LO 32

Air Marking was on site and ground the white line into a skip on Michigan at Chippewa in the round about.

Thursday, December 1, 2016

12-1-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Cloudy drizzle PM cloudy drizzle  
HI 38 LO 32

Martell was on site and worked on placing the push ped on thesouth east corner of Chippewa and Main. They also worked on adjusting the push ped on the North east corner of Chippewa and Main (island).

No other work took place.

Wednesday, November 30, 2016

11-30-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Sunny PM Sunny  
HI 50 LO 41

Martell removed the Sign on Ewing. 

No other work took place today.

11-29-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Rain/Sunny PM Sunny  
HI 56 LO 41

No one on site today

Monday, November 28, 2016

11-28-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Rain PM Rain  
HI 50 LO 41

No one on site today

Wednesday, November 23, 2016

11-23-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Rain PM Rain  
HI 44 LO 36

No one on site today

Tuesday, November 22, 2016

11-22-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Cloudy PM Cloudy  
HI 41 LO 27

No one on site today.

Monday, November 21, 2016

11-21-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM SUNNY PM SUNNY  


HI 40 LO 30

No one on site today.

Saturday, November 19, 2016

11-19-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Cloudy Windy Snow PM Cloudy Windy Snow  
HI 38 LO 34

No one on site today.

Friday, November 18, 2016

11-18-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Sunny  PM Sunny  
HI 68 LO 46

No one on site today.

Meeting MINUTES
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
11-18-16


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1.       Traffic Closure Updates
A.       Saint Joe will open from Western to Sample on Tuesday, and LaSalle to Western Wednesday afternoon (11-23-16). The traffic signal at Bronson and Main won’t start until Dec. 1st.

Utility Relocation Issues:
AEP:        Jefferson and Michigan will be open for the weekend, and then closed again Monday-Wednesday. After Wednesday only southbound Michigan between Jefferson and Wayne will be closed.

Robert Henry:
1.       Washington and Michigan is done and paved.
2.       Vault LaSalle and Michigan N/W Corner has been approved to work on, will coordinate time with Rieth-Riley
3.       Vault at Main and Washington S/E  Corner work will begin the 2nd week in December and be done the 1st week in January
4.       Casting west side of Saint Joe by Morris is done.

NIPSCO/InfraSource:   
            
Comcast: 

                AT&T:     

Water Dept:   Has received as builts from Woodruff. Also concerned that some hydrants might be too high, and will get Rieth-Riley a list of ones of concern

Transpo:    Had questions about signal timing and when the signal at South St and Michigan will be up.
               
Metronet:  Not at meeting
 1.  WIFI  on Saint Joe still has not been moved
2.       Foundation at Century Center removed
                 

Utilities Q/A

INDOT: Questions:   

Stakeholder Questions: The hospital asked about a walkway from their parking lot east of Michigan. Rieth-Riley put one in near the Marion roundabout crosswalk but they would like one further north for people heading to Navarre. They also had questions about the pedestrian signs north of Bartlett and putting the signs laying on the ground back up. They worried about the drop off on the edges of the sidewalk, but sod should be in everywhere from LaSalle north this year.

10:00 am 10:10 Break Utility and Stakeholders can leave


Action Items
               
1             Upcoming work for the week: Decorative brick along Main St. pouring sidewalk and opening St. Joe to two way traffic
2             Western And Main South West Corner: JPR will lay it out
3             Scheduled \opening
     A. Traffic Signals- Colfax and LaSalle today and tomorrow
     B. Markings- St Joe will hopefully be done by the end of the day.
4             Chippewa walk trough/ Traffic signal work: 30 mph signs in today, walk through first week in December
5             Snow Flags- Will take a couple weeks to order, will come up with a count
6             Landscape Sod and Trees- North of LaSalle will be done this year, trees down Main St. may be questionable to get in this year.
7             Main Street Bridge lighting- Pemberton Davis to get a quote next week. Will not do the work until bridge is no longer populated by homeless people for safety concerns.
8             Getting ready for Winter/expectations
A.      Cross walks- One concrete crew will be staying onboard as long as the weather holds out to continue getting as many curb ramps in as they can before winter.
B.      Clean Man Holes- before winter
C.      Temp Tape- to be removed
D.      Behind curb drop-offs- Stone and 8’s will be in so it will only be around a 4 inch drop. Fiberglass markers will be put up to show where the drops are for vehicles plowing the sidewalk and cycle track.
E.       Planters at the court house- DTSB to move
Reith Riley Construction Concerns/Questions:

City Concerns/Questions: The city wants to make sure the century center is accessible through the winter, with walks at Jefferson and Washington. They would also like the curb ramps that have been torn out for months filled in at Western and Monroe/Michigan. Rieth-Riley will work with Pemberton Davis, and have them finish work in the ones that need the least done in order to be able to pour the most curb ramps possible before winter.

The order decided on for installing traffic signals is to do Jefferson/St. Joe, then LaSalle/Main and LaSalle/Lafayette, then Washington/St. Joe
                               
 Next weekly progress meeting 11-18-16




Thursday, November 17, 2016

11-17-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Sunny  PM Sunny  
HI 68 LO 46

No one on site today.

Wednesday, November 16, 2016

11-16-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Sunny  PM Sunny  
HI 63 LO 36

No one on site today.

Tuesday, November 15, 2016

11-15-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Sunny  PM Sunny  
HI 58 LO 34

No one on site today.

Monday, November 14, 2016

11-14-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Sunny  PM Sunny  
HI 54 LO 29

No one on site today.

Saturday, November 12, 2016

11-12-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Sunny  PM Sunny  
HI 48 LO 25

No one on site today.

Friday, November 11, 2016

11-11-16

Controlling Operation: Fence
Fraction of Day workable 10/10
AM Sunny  PM Sunny  
HI 55 LO 50

Martell was on site to work on the push peds at Chippew but was unable to due to the locations of the foundations would not work.

 No other work took place on this contract today. 

Thursday, November 10, 2016

11-10-16

Controlling Operation: Fence
Fraction of Day workable 10/10
AM Sunny  PM Sunny  


Hi 62 Lo 35

Reith Riley had a 2 man crew replace the sod they tore up yesterday.

No other work took place today.

Wednesday, November 9, 2016

11-9-16

Controlling Operation: Fence
Fraction of Day workable 10/10
AM Cloudy Rain  PM Cloudy Rain  
Hi 62 Lo 44

Reith Riley was on site and worked on the drainage issue at the Palmer Funeral home yard. Found a 8 inch line from Plalmers drains just west of the bend in the sidewalk,

Miller fence was in and placed the decorative picket fence on the south east corner of Michigan and Chippewa.

No other work preformed today.

Tuesday, November 8, 2016

11-8-16

Controlling Operation: Fence
Fraction of Day workable 10/10
AM Cloudy Rain  PM Cloudy Rain  
Hi 62 Lo 44



No work preformed on this project today.

Monday, November 7, 2016

11-7-16

Controlling Operation: Fence
Fraction of Day workable 10/10
AM Sunny  PM Sunny  
Hi 69 Lo 44

No work preformed on this project today.

Sunday, November 6, 2016

11-5-16

Controlling Operation: Fence
Fraction of Day workable 10/10
AM Sunny  PM Sunny  
Hi 70 Lo 38



Reith Riley had no one on site today.