Saturday, April 30, 2016

4-29-16

No work was preformed on this division today.

Reith Riley is scheduled to start work on Division A Monday May 2nd.

4-28-16

No work was preformed on this Division today

Meeting Agenda
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
4-29-16


Regarding:
Project 116-001 One Way to Two Way Conversion Weekly
Progress Meeting

Construction and Utilities

ITEMS TO BE DISCUSSED
9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
Reith Riley will start working on Division A at Chippewa and Main St. They will have the far right lane closed on Main St. at that intersection.

Division B they work on removing the Mar Main pharmacy and build the temporary road from Michigan to Marion. At Bartlett Street they will work on curb and pavement between Saint Joe and Michigan. They will also work on structures west of Michigan.

Utility Relocation Issues:
                AEP:   Bartlett Street: AEP will set back some street lights on Bartlett Street, all other work on Bartlett is complete. On Marion Street the pole relocation east of Michigan has been completed. When this work was done it blackened the east side of Michigan between Marion and Navarro. At Chippewa the Transmission Line running east and west is still not relocated. Tony Marcia anticipated AEP will start working on this area in another week and should be done by the end of May.

                Robert Henry: is working at Wayne and Main St. They are 4 days ahead of schedule.

                NIPSCO: Will be bringing in a third crew and the will start working from Lassalle to Madison on Main St. The City is still concern about the crossing at Colfax and Main.
                Comcast: We’ve completed Bartlett, hope to have the city permit soon and start Chippewa next week. I believe Rogers question about the progress down town was answered by Rick Walstra last week! Thanks

                US Signal: Has the Engineering work completed on Chippewa Street and is working on getting the permits. They will then get started. US Signal will be responsible to move the Windstream cable that is bundled with its cables located on the East side of Michigan.

                Windstream on Main Street is taken care of. On Michigan Us Signal will be handled the relocation. 
                AT&T: Did not show up. They still have the issue at the ally on Bartlett street just west of Michigan. A new issue arose with the AT& T vault on the North West corner of Bartlett and Michigan. A meeting will be set up to meet with AT&T, Reith Riley, JPR and the City.        

                Water Dept. was unable to attend. They called and had no issues.

Additional RW and Encroachments:
                Division A
1.       Cavalry Temple
2.       Palmer Funeral- Home, closed yesterday, Asbestos inspection can take place later next week.
3.       XB Real Estate-is clear
4.       Sandra V Case- City will move out on May 17th, can get asbestos testing on May 18th get officially May 22nd.
                Division B
1.       First Source-property cleared
2.       Fifth Third bank-Pay Voucher on the 17th.
3.       QDI Realty- property Cleared
4.       Memorial Hospital Parcels 1, 2 & 3- the City has right of entry
5.       Burkhart sign- The sign will either be removed by Burkhart or by Reith Riley by the 17th of May. I will contact Bob Strasberg about getting the power disconnected to the sign.

Submittals (List at Meeting):

Action Items
                                1 QC/QA concrete- Reith Riley needs to get new price to the City.
                                2 QC/QA HMA- Reith Riley needs to get new price to the City
                                3 RFI # 4 Blocks- The city is meeting on this topic Monday
                                4 Permit to enter River/cofferdam- Has been received and Reith riley can enter the River to do the work from May 2nd to May 13th.
                                5 Asbestos at Mar Main removals by Memorial Hospital Subcontractor. This work has been completed and a letter will be forwarded confirming this.
                                6 Sign for office- Pemberton Davis is having the graphics main and ill place it next week.
                                7 Placement of Message boards for Marion and Bartlett- Corbitt requested the signs at Park and Angela be moved for better sight distance. He also wants the sign North of Lassalle moved to the parking area at Lassalle and Michigan.
                                8 Drive for Hospital work trailer building on Bartlett- received the revision yesterday.
                                9 Chase Tower (Main Street) The City will investigate a possible vault out under the sidewalk
                               

Reith Riley Construction Concerns/Questions:

City Concerns/Questions: Corbett asked about the Video Cameras that need to be placed. Martel is going to meet with the City Monday.
Corbett informed Reith Riley to wait on working on South Street and Michigan and South and Main as long as they can. The removal of the signs may not happen. They need to proceed per plan on all other locations.
                               
 Next weekly progress meeting 5-6-15


Wednesday, April 27, 2016

Tuesday, April 26, 2016

Monday, April 25, 2016

Saturday, April 16, 2016

4-15-16

No work preformed on this division today.

                                               One Way to Two Way Street Conversion
Weekly Progress Meeting 4-15-16

Started with Introductions
Reith Riley then gave an over view of the coming work. Reith Riley plans on placing the 20 inch water line relocation at Bartlett Street. This work will cause traffic on Michigan to be reduced to 1 lane in each direction and Bartlett Street will be closed to the West and will only allow traffic heading north to turn right. Reith Riley will also be working on the east side of Michigan between Bartlett and Angela Boulevard replacing ramps. Reith Riley will have a crew putting Bartlett Street back together between Riverside and Saint Joe. Once that is reassembled Bartlett will be closed between Saint Joe and Michigan and removals will begin. Pemberton Davis will be doing traffic work on Michigan and Indiana removing traffic signals that have already been bagged.
Memorial Hospital had concerns about the removals between Saint Joe and Michigan in regards to their drive for the work trails just west of Saint Joe.
The Water Department was concerned about deliveries to their facility on Bartlett Street. They have a semi delivery weekly that comes from the North and the only accesses to plant is off of Bartlett Street. Special accommodations will be made to assist the delivery.
Utility Relocations
AEP Bob The line on riverside down the ally has been relocated to a temporary pole. Comcast and AT& T have been informed to get their work done down the alley.
AEP Tony was not present and could not give an update on the Chippewa work
Nipsco Phil The work at Bartlett should be completed by Monday.
Comcast was unable to attend.
US Signal was unable to attend
Windstream Bob will check with Tony
Utility Upgrade Robert Henry gave an over view of the upcoming work and the past work at this time they are on schedule.
Nipsco gave an over view of the work in the down town area
A break was taken and the utilities and stakeholder where allowed to leave.
Additional R/w was then discussed Reith Riley pressed to get the Mar Main property as soon as possible so demolition can take place, since asbestos is in the building. They also pressed to try and get the Sandra Case home before May 21st.
After reviewing the Submittals the flowmeter is still out for woodruff submittal 23 witch is late for due to the flowmeter. The Tesco Cabinet single phase is still out for the Pemberton Davis #6 which is due Monday. After further talks it was determined more help was needed to keep up with submittals. Toy will see if he can find more help.
Reith Riley then had questions about QC/QA Concrete whether the city will be paying bonuses per state spec. Upon further discussion. Reith Riley will submit a new price for non QC/QA concrete and the city will determine what it wants to do. Reith Riley will also submit a price for non QC/QA asphalt due to the coring of the asphalt.
The revision 6 Mast arms was a concern, on how poles at intersections can be taken away and used else wear without affecting the intersection at which the old mast arm is removed. Corbett suggested using the poles from the intersections that are being closed in the downtown area, after reviewing the plans the intersections downtown are not being closed down. A meeting will be set up next week to further discuss the phasing and used pole placement.
Reith Riley also wanted a clarification on the brick pavers being used due to the confliction in the plans details and special provisions. The city wants to be uniform in the details and will review the issue.
The asbestos at the Mar Main building will need to be abated. Reith Riley will have this done as soon as the city has the property owned. A change order will be issued to do the work.
Reith Riley voiced concerns about the sidewalk ramps elevations not working out the plans and having the proper cross slopes and grades.
Reith Riley also questioned the sprinkler system allotment. Since payment is made by the Square Yard, and how will repairs be compensated for.
The City Concerns: the cameras for the down town area. The city will purchase the cameras threw a third party as soon as Reith riley gives the city a price. Then Reith Riley will install the newly purchased cameras.
Additional revisions forth coming at Chippewa are the additional R/W, sidewalk, and an additional driveway to the parking lot. At the Marion round about a loading zone will be added to Main Street in front of the apartment buildings.     

4-14-16

No work preformed on this division today.

Wednesday, April 13, 2016

Tuesday, April 12, 2016

Monday, April 11, 2016

Friday, April 8, 2016

Thursday, April 7, 2016

Wednesday, April 6, 2016

4-6-16

No work was preformed on this division today.

4-5-16

No work was preformed on this Division today

                                                  .4-5-16 Progress Meeting
                Started with Introduction
                Then Reith Riley was to introduce an updated schedule.
Reith Riley did not give an updated schedule, the reasoning was they did not have the submittal back for structure 802, or rim elevations for Chippewa or Marion. They also noted the lack of a permit for getting into the River. They proceeded to give an oral presentation. They will be working at Marion and Michigan moving the water 20” waterline which is anticipated to take the rest of the week. They will be working on removals on Bartlett from Riverside to Saint Joe this week. They plan on working on Michigan Street north of Bartlett to Angela Boulevard, on the intersections pedestrian ramps, working on the east side first and then moving to the west side. 
                Utilities
AEP Bob Strasburg:  AEP will be out today to remove the light poles on Bartlett from Riverside to Saint Joe. Which is a week later than scheduled. They will then work on the line down the alley east of Michigan next week, and should take a day to set temp pole.
AEP Tony Macias gave an update on the Chippewa intersection and it was stressed that he be done with his work before the first of June. He also filled us in that the Windstream line was on Main Street not Michigan as originally thought.
Nipsco will be done with the Bartlett street intersection by April 15th.
Comcast did not attend, but Jay Castello did email stating, I’ll run by today to see if the R/W is staked and probably wait till the trees have been removed before I bury the new line. At Chippewa I’ll check with my contractor to see when they will start and let you know. On Main north of Chippewa the underground was installed yesterday and hoping to have the service removed from an old transmission pole for the project. I’ll keep you posted with updates.
US Signal did not attend.
                Utility Upgrades
AEP/Robert Henry gave a brief time frame on the work and how it is progressing. The work at South Street is complete. They have moved to Main and are working from Columbus Court to Jefferson St. and this work should be completed by the 18th. They will then move south from there.
Nipsco/ Phil Griffin: while working on the Nipsco upgrades downtown they ran into a vault on Main St. North of Colfax to the alley. The vault goes all the way out to the curb line.
                Took break and utilities and businesses left at this time
                Additional RW
Division A
1.       Cavalry Temple –sign under negotiation
2.       Palmer Funeral Home - agreed
3.       XB Real Estate-closure need
4.       Sandra V Case – available on May 21st
                Division B
1.       First Source-paying Tuesday
2.       Fifth Third bank-
3.       QDI Realty- pay Tuesday
4.       Memorial Hospital Parcels 1, 2 & 3- closed last week
5.       Transpo- recorded
6.       Billboard Burkhart

Submittals Division A
Martell 1 item 177 & 232 are still out was due 3-25-16
 Reith Riley 4 missing storm and casting due -4-6-16
                Submittals Division B
Woodruff 1 Structure 802 due 3-23-16 Roger called Reith Riley had it by the end of the meeting.
All other submittals at this time in good standing.
Reith Riley still needs rim elevations for Marion and Chippewa. Roger called and Marion was given to Reith Riley before the end of the meeting.
                Reith Riley Construction Concerns
Was wanting more information on the vacuum line running out of the hospital east down Marion and the vacuum line running to MAR Main.
Joint lay out for Main by Bronson will be State standard.
They asked about the duct bank on Michigan by Madison at the current location and it should be out of the way.
Reith Riley needs to send a letter to the City and then the City will request a waiver
 from the DNR to work in the River.
Tanner asked about the permits and occupancy bond. He was having trouble getting them from the City Toy looked into it during the meeting and the fee will be waived.
Reith Riley was having trouble with residence parking on Bartlett after it had been closed.
                City Concerns
Field office is still not ready to move in.
Railroad Insurance- Reith Riley needs to get for Michigan St. and I need to get a precon scheduled with the Railroad.
Video Camera’s for the downtown area: Corbitt is going to review  the option of placing them on the buildings verse poles.
The next progress meeting will be 4-15-16 at 9:00 AM

  