Friday, December 16, 2016

12-16-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM cloudy light snow   PM partly cloudy  
Hi 18 Lo 2

No work preformed today due to the weather wind chill below zero

Thursday, December 15, 2016

12-15-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM cloudy light snow   PM partly cloudy  
Hi 8 Lo -2

No work preformed today due to the weather wind chill below zero

Wednesday, December 14, 2016

12-14-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Mostly Sunny   PM Mostly Sunny  
Hi 18 Lo 2

No work preformed today due to the weather wind chill below zero

Tuesday, December 13, 2016

12-13-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Cloudy snow   PM Cloudy  
Hi 26 Lo 15

No work preformed today due to the weather 

Monday, December 12, 2016

12-12-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Cloudy   PM Cloudy  
Hi 31 Lo 15

No work preformed today due to weather.

Friday, December 9, 2016

12-9-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Cloudy Snow  PM cloudy Snow Windy 
Hi 25 Lo 15

No work preformed today due to weather 

Thursday, December 8, 2016

12-8-16

Controlling Operation: Signal work
Fraction of Day workable 0/10
AM Cloudy Snow  PM cloudy Snow Windy 
Hi 28 Lo 15

No work preformed today due to weather 

Wednesday, December 7, 2016

12-7-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Partly Cloudy  PM cloudy
Hi 37 Lo 27

A prefinal inspection was held at 1:00 PM  

Chippewa Punch List
                                                Chippewa Roundabout
1.       Paint Conduit sticking up for Cavalry Temple old sign Electric
2.       Grates fins facing right direction Several
3.       Plastic on ramp Tiles
4.       Route and seal cracks on all new concrete curb and concrete in cavalry temple lot next to curb
5.       Trees Leaning on Chippewa North Side between main and Michigan
6.       Temp tape (trash) on Main/Chippewa island
7.       Remove  ramp and replace with curb and sidewalk on south side of Chippewa between Main and Michigan
8.       Add 2 more sets of round about arrows south on Michigan
9.       Get extra signs up on cable span for round about calling out Main and Michigan.
10.   Get geotextile off of drains south west corner Mich and Chippewa
11.   Add ground Mounted signs for Michigan and Main south of Roundabout
12.   Put up sign by mail box that was stolen R8-3(mod)
13.   Cover for irrigate back flow preventer
14.   Irrigation lines lower below curb on west side
15.   Irrigation wiring on east side
16.   Couple of parking stalls need lines finished  

Donmoyer and Michigan
1.       Tape on signal pole foundation nuts from painting remove
2.       Plastic on crosswalk tile remove
3.       Covers on traffic signal poles

Ewing and Michigan
1.       Concrete sidewalk at Tesco
2.       Tape on signal pole foundation nuts from painting remove
3.       Change out 3m head

Ewing and Main
1.       Concrete around the walk/wait on the North East corner
2.       Change out the 3m heads

3.       West of main Right arrow turn to right/straight

Tuesday, December 6, 2016

12-6-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Cloudy  PM cloudy  


HI 40 LO 32

Martell worked on the intersection on Michigan and Ewing replacing the Cabinet and controller. They also worked on the intersection of Main and Ewing.

Reith Riley poured the colored concrete island back at the intersection of Chippewa and Main. 

no other work took place today.

12-5-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Cloudy  PM cloudy   


HI 38 LO 31

Martell worked on replacing the cabinets and controllers at the intersection of Donmoyer and Michigan. They also worked on the Intersection of Ewing and Michigan.

No other work took place today.

Friday, December 2, 2016

12-2-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Cloudy drizzle PM cloudy drizzle  
HI 38 LO 32

Air Marking was on site and ground the white line into a skip on Michigan at Chippewa in the round about.

Thursday, December 1, 2016

12-1-16

Controlling Operation: Signal work
Fraction of Day workable 10/10
AM Cloudy drizzle PM cloudy drizzle  
HI 38 LO 32

Martell was on site and worked on placing the push ped on thesouth east corner of Chippewa and Main. They also worked on adjusting the push ped on the North east corner of Chippewa and Main (island).

No other work took place.