Tuesday, May 31, 2016
Friday, May 27, 2016
Thursday, May 26, 2016
5-26-16
Controlling Operation: Phase 2
Fraction of Day Workable: 10/10
Hi 84 Lo 64
Weather AM Cloudy, Humid PM Cloudy, Humid
No work by the contractor was preformed today.
Turnkey was on site for US Signal, and finished pushing conduit at the intersection of Chippewa and Michigan. Hook-ups are all that is remaining for Turnkey's work in the area.
AEP continued their work relocating their three phase tie at the Chippewa intersection.
Fraction of Day Workable: 10/10
Hi 84 Lo 64
Weather AM Cloudy, Humid PM Cloudy, Humid
No work by the contractor was preformed today.
Turnkey was on site for US Signal, and finished pushing conduit at the intersection of Chippewa and Michigan. Hook-ups are all that is remaining for Turnkey's work in the area.
AEP continued their work relocating their three phase tie at the Chippewa intersection.
5-25-16
Controlling Operation: Phase 2
Fraction of Day Workable: 10/10
Hi 84 Lo 61
Weather AM Sunny PM Partly Cloudy
No work by the contractor was preformed today.
Turnkey was on site for US Signal pushing conduit at the intersection of Chippewa and Michigan.
AEP continued their work relocating their three phase tie at the Chippewa intersection.
Fraction of Day Workable: 10/10
Hi 84 Lo 61
Weather AM Sunny PM Partly Cloudy
No work by the contractor was preformed today.
Turnkey was on site for US Signal pushing conduit at the intersection of Chippewa and Michigan.
AEP continued their work relocating their three phase tie at the Chippewa intersection.
Tuesday, May 24, 2016
5-24-16
Controlling Operation: Phase 2
Fraction of day workable 10/10
Hi 85 Lo 60
Am Sunny Pm Sunny
No work by the contractor was preformed today.
Turnkey was on site for US Signal boring at the intersection of Chippewa and Michigan.
Gordon pulled Comcast fiber at the intersection of Chippewa and Michigan.
AEP began work relocating their three phase tie at the Chippewa intersection.
Fraction of day workable 10/10
Hi 85 Lo 60
Am Sunny Pm Sunny
No work by the contractor was preformed today.
Turnkey was on site for US Signal boring at the intersection of Chippewa and Michigan.
Gordon pulled Comcast fiber at the intersection of Chippewa and Michigan.
AEP began work relocating their three phase tie at the Chippewa intersection.
Monday, May 23, 2016
5-23-16
Controlling Operation: Phase 2
Fraction of day workable 10/10
Hi 78 Lo 53
Am Sunny Pm Mostly cloudy Sunny
No work by the contractor was preformed today.
Turnkey was on site for US Signal boring at the intersection of Chippewa and Michigan.
Gordon pulled Comcast fiber at the intersection of Chippewa and Michigan.
Fraction of day workable 10/10
Hi 78 Lo 53
Am Sunny Pm Mostly cloudy Sunny
No work by the contractor was preformed today.
Turnkey was on site for US Signal boring at the intersection of Chippewa and Michigan.
Gordon pulled Comcast fiber at the intersection of Chippewa and Michigan.
Friday, May 20, 2016
5-20-16
No Work Preformed on this Division today
The keys to the Case house was given to Reith Riley.
The keys to the Case house was given to Reith Riley.
Thursday, May 19, 2016
Monday, May 16, 2016
5-16-16
Controlling Operation: Phase 2
Fraction of day workable 10/10
Hi 67 Lo 38
Am Mostly Sunny Pm Mostly cloudy
No work by the contractor was preformed today.
Comcast worked on boring on Chippewa running east to west.
Fraction of day workable 10/10
Hi 67 Lo 38
Am Mostly Sunny Pm Mostly cloudy
No work by the contractor was preformed today.
Comcast worked on boring on Chippewa running east to west.
Saturday, May 14, 2016
5-13-16
No work preformed on this division today.
Meeting Agenda
Meeting Agenda
Meeting With:
|
|
|
|
Meeting Date:
|
|
|
|
Regarding:
|
|
|
Construction and
Utilities
|
ITEMS TO BE
DISCUSSED
The Weeks up Coming
Events/Schedule
Division A – Reith Reilly plans to continue preliminary
work. The asbestos testing is expected
to be completed by early next week.
Division B – Anticipating the Tuesday closures, Reith Reilly
plans to have demolition crews in 3 areas with concrete crews continuing their
work on Bartlett. They plan to begin
storm work as early as Tuesday afternoon, immediately following the demolition
crews.
Utility Relocation Issues:
AEP:
Bartlett Street lights have been removed.
Marion Street: Robert hennery plans
on finishing the removal of street lights this
Weekend
Chippewa:
AEP still has not removed their
line from the pole at Chippewa, but they plan to start work next week. Comcast and US Signal were waiting for AEP,
but have taken measures to complete their work in spite of AEP’s delays.
Robert Henry:
Robert Henry will complete their
work on the south east corner of Main & Western on Saturday. They plan to begin work on Marion Street
starting next week. The crossings at
Washington, Jefferson, and Western (utilizing a night closure for Western) are
expected to be done by June 8.
NIPSCO/InfraSource
NIPSCO will be done at the
Columbia Court area by the morning of the closure on the 17th. Their work on Main between Madison and Marion
was expected to have been completed today, but the water main breakage caused
their gas line to fill. As a result,
their work here has been set back a few days and is now expected to be done by
the 23rd. They plan to have
all work north of Lassalle done by the 23rd. There were some concerns about untonable gas
lines on Bartlett. Phil from the utility
will have someone go on site to check on these, but he believes the lines have
already been shut off and are a nonissue.
Comcast:
Jay couldn’t make the meeting, but
he relayed that Comcast will start work on Chippewa on the 16th and
has plans to be out of the area by June 5th.
The pole on Marion east of Main may need to be
held due to its location in reguards to the storm sewer line, since Comcast and
AT&T are still on it.
US Signal:
Charlie O. of the utility has
plans to splice beginning June 3rd.
US Signal will be off of the pole and out of the Chippewa intersection
by June 5th.
AT&T:
No one for AT&T came to the
meeting. I will call Dennis to check
up. The vault on Michigan at Bartlett is
preventing Reith Reilly from setting 2 structures. The line at Marion and Michigan is still
scheduled to be moved in the next week.
Water Dept.
The Water Department discovered
two broken valves that need to be fixed as soon as possible without disrupting
the construction schedule. One valve is
located on Main Street near the intersection with Lassalle. The other is located on Lassalle Ave near
Main and will require two days to repair.
Ed from South Bend Water has said the work could be completed on a
weekend with traffic restricted to one lane and a flagger present.
INDOT:
INDOT was a no
show.
Transpo:
Transpo just wanted to confirm the
placement of the Temporary Access Lane to the Transpo lot.
Metronet
Metronet has a rigid conduit near
Bartlett that may need to be lowered so that Reith Reilly can continue their work
in the area. If the conduit needs
lowered Pemberton Davis will do this work, while they are in the area. Some
work will also need to be done to determine the fiber line in the handhole
location and splicing capabilities.
Stakeholder
Questions:
Larry with
Memorial Hospital inquired about the signage regarding the Michigan Street
detours. Local Traffic Only signs have
been added for the south bound traffic north of the river and for the north
bound traffic at Lafayette & Marion.
A No Outlet sign will also be added for north bound traffic on
Michigan. Larry will notify EMS of the
closures and detour routes.
Additional RW and Encroachments:
Division A
The Case house will be vacated on
the 16th and the City will take ownership of the house on the 20th
Division B
Corbitt will have a resolution for
the Burkhart sign this afternoon following today’s meeting. If Burkhart refuses to remove the sign
themselves, a special meeting to call for Condemnation will be held on the 16th
to give AEP the legal right to cut the power.
The sign itself can be removed at any time, but likely won’t be down
until the 19th or 20th.
The foundation can be removed once the power is taken care of.
Submittals (List
at Meeting): No issues with submittals
Action Items
1 MCI
Quentin, representing MCI,
provided drawings detailing the extent of the work MCI has yet to do. They have a conduit on the northwest corner
of Main and South Street that needs to be lowered as soon as possible. MCI will be placing test holes at other
intersections on Main, as well. MCI also
has work to do on the Southwest corner of Main and Washington. Quentin will relay that this work needs to be
started next week.
2 QC/QA HMA
A
change order is being written regarding the QC/QA HMA.
3 Redesign on Mich/Marion
The structures on Michigan west
side between Madison and Lasalle may need to be altered to tie into the
existing structure on Lasalle. Another
structure may need to be added at the Michigan and Madison intersection. The remaining structures between Madison and
Marion on Michigan are cast in place. A
meeting has been set with Lawson Fisher on Monday to go over these details.
4 Chase Tower (Main Street)
There is a vault underneath the
Chase Tower that needs to be avoided.
Reith Reilly will need access to do a sawcut and then will avoid
sidewalk work and plan to work outside of the problem area. Tony (Reith Reilly) will review the layout of
the curb and get a plan for the construction, working with Leonidas (Chase) to
determine how much work can be done.
5 RFI #4 Permeable Block
Division A
consists of all non-permeable brick pavers with non-permeable detail. Division B will have permeable brick pavers
for the splitter islands and buffer area.
Reith Reilly is concerned that the special previsions for the
non-permeable pavers do not include all of the components of the pay item. A meeting has been set for Tuesday at the
field office with Reith Reilly and the city to work out the details of these
concerns.
Reith Riley Construction
Concerns/Questions:
Tony
wanted to confirm that loop sealant with no backer rod is being used for the
concrete joints on Bartlett. It was also
decided that the signals at the intersection of Michigan and North Shore Drive
should be set to red flashers and that the lights should not be bagged for the
closure.
City
Concerns/Questions:
Next weekly progress meeting 5-20-15
Thursday, May 12, 2016
5-12-16
Controlling Operation: Concrete
Fraction of day workable 6/8
Hi 76 Lo 62
Weather AM Partly Cloudy PM Cloudy Rain
Reith Riley placed backfill around the curbs at Chippewa and Main St North west corner.
Had a meeting with today with AEP, Comcast, Reith Riley and Lawson Fisher on site to review the condition of the utilities relocation's. Everyone claims they will be done by June 5th.
Fraction of day workable 6/8
Hi 76 Lo 62
Weather AM Partly Cloudy PM Cloudy Rain
Reith Riley placed backfill around the curbs at Chippewa and Main St North west corner.
Had a meeting with today with AEP, Comcast, Reith Riley and Lawson Fisher on site to review the condition of the utilities relocation's. Everyone claims they will be done by June 5th.
Wednesday, May 11, 2016
5-11-16
Controlling Operation: Cub and Gutter
Fraction of day workable 8/8
Hi 76 Lo 56
Weather Am Partly Cloudy Pm Partly Cloudy
Reith Riley finished pouring the curb on Phase 1. Once the curb was poured it was apparent the grade change will be an issue during construction.
Fraction of day workable 8/8
Hi 76 Lo 56
Weather Am Partly Cloudy Pm Partly Cloudy
Reith Riley finished pouring the curb on Phase 1. Once the curb was poured it was apparent the grade change will be an issue during construction.
Tuesday, May 10, 2016
5-10-16
Controlling operation: concrete curb and gutter
Fraction of day workable 0/8
Hi 65 Lo 48
Weather Am Rain PM Rain
No work preformed today due to rain.
Fraction of day workable 0/8
Hi 65 Lo 48
Weather Am Rain PM Rain
No work preformed today due to rain.
Monday, May 9, 2016
5-9-16
Controlling Operation: Curb and Gutter Placement
fraction of day workable 8/8
Hi 58 Lo 45
Weather Am Light Rain PM cloudy Mist
Reith Riley placed forms and poured the curb and gutter at Chippewa and Main.
I talked with Charlie O. of US Signal to get the cable on Chippewa started. he still needs permits from the City.
fraction of day workable 8/8
Hi 58 Lo 45
Weather Am Light Rain PM cloudy Mist
Reith Riley placed forms and poured the curb and gutter at Chippewa and Main.
I talked with Charlie O. of US Signal to get the cable on Chippewa started. he still needs permits from the City.
Saturday, May 7, 2016
5-6-15
Controlling operation: Structure placement.
Fraction of day Workable 10/10
Hi 76 Lo 48
Weather AM Sunny PM Sunny
Reith Riley rebuilt the structure on the corner of Chippewa and Main and backfilled the pipe structures at this intersection.
The weekly progress meeting was held today. See min. below.
Meeting Minutes
Fraction of day Workable 10/10
Hi 76 Lo 48
Weather AM Sunny PM Sunny
Reith Riley rebuilt the structure on the corner of Chippewa and Main and backfilled the pipe structures at this intersection.
The weekly progress meeting was held today. See min. below.
Meeting With:
|
|
Meeting Date:
|
|
Regarding:
|
|
Construction and Utilities
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
Reith Riley plans on finishing up Division A Phase 1.
They are going to Demo Mar Main Pharmacy. They will work on sidewalk and approaches on
Bartlett east of Michigan. West of Michigan on Bartlett they will work on
concrete paving and subgrade work. They also plan on doing water main work on
Main St. just south of Marion
Utility Relocation Issues:
AEP:
The light North of Bartlett on the east side will be taken down next
week. 25 lights will be taken down late
next week at the intersection on Michigan and Marion and Main and Marion
Tony from Reith Riley will be getting with Fran from AEP to go over the
down town area on light removals.
Tony
Macia with AEP has not started the relocation work on Chippewa yet. He said
they should be next week and be finished by the last week of May.
Robert Henry:
Robert hennery is done by the Library and are continuing South. They
plan on closing Washington on the 16th or 17th. They are
still ahead of schedule.
NIPSCO/InfraSource
Lassalle Ave work is completed. They are having trouble going down the
Columbia Court Area due to a lot of abandoned foundations. They are going to
have to open cut across main at Colfax due to all the vaults in the
intersection. This work will have to be completed by the 16th. They
will be doing 2 lanes at a time. All work will be completed on Lafayette St. by
the 16th of May all travel lanes and parking lanes will be free from
work and open to traffic. Toy will be checking on the work that HRP is doing on
Lafayette to help to get the lanes opened up for the 17th closure of
Marion and Bartlett.
Comcast:
No one showed up for Comcast. I will call and get an update.
US Signal:
No one showed up. I called Charlie and they still don’t have their
permits.
AT&T:
No one for AT@T came
to the meeting.
Bartlett
Street Ally East of Michigan the pole is still in the way and was supposed to
be removed Monday. The vault at Michigan and Bartlett will begin on Monday. The
line at Marion and Michigan is scheduled to be moved in the next 2 weeks.
Water Dept. was a no show
INDOT:
was a no show
Transpo was wanting an
intersection schedule. I will get that to them. They also wanted to make sure
the drive construction on South St. will not affect pickups. Transpo has a bus
that parks on South St. to do pickups, which could be affected during
construction.
Metronet
needs notified to do the work at the South East corner Bartlett and Michigan to
the handhole.
Stakeholder; I
notified Larry Lies of Memorial that the cross walk at Bartlett and Michigan
may be lost due to the work that AT@T is doing at the intersection may affect
the wiring to the traffic signal. Toy is going to contact the Chase Tower when
work starts up in the area to have the barrier wall moved and to have the
window installation stopped when Reith Riley is working in the area. A sleeve
will need to be placed for electric for signs placed later by the hospital.
10:00 am 10:10 Break Utility
and Stakeholders can leave
Additional RW and Encroachments:
Division A
1.
Sandra V Case: will move out on the 17th
can do asbestos check on the 18th.
Division B
1.
Fifth Third bank: should not be an issue
2.
Burkhart sign: Reith Riley needs to know
before the 17th if they are doing the work or if Burkhart is going
to have the sign removed before the 17th.
Submittals (List
at Meeting): no issues with submittals
Action Items
1 QC/QA
concrete: This will be a no cost change order.
2
QC/QA HMA : Reith Riley is still working on a price.
3
Mar Main Demo : The gas still needs disconnected so the demo work can be done.
This temporary road can’t be built with Mar Main still standing.
4
Chase Tower (Main Street):
5
RFI #4 Permeable Block: Reith Riley should receive the reply by the end of the
day.
Reith Riley Construction
Concerns/Questions:
City
Concerns/Questions:
Next weekly progress meeting 5-13-15
Thursday, May 5, 2016
5-5-16
Controlling Operation: Structure Placement
The South Bend Water deptment delivered a casting to replace an existing manhole lid that was broken. The casting was broken prior to any work preformed at this site.
Fraction of day workable 10/10
Hi 64 Lo 45
Weather AM Sunny PM Sunny
Reith Riley had a crew placing pipe pipe on the North West Corner of Main and Chippewa. While placing pipe a AT&T line was struck. Two lines inside the cable where severed. AT&T will be onsite for repairs tomorrow.
The South Bend Water deptment delivered a casting to replace an existing manhole lid that was broken. The casting was broken prior to any work preformed at this site.
Wednesday, May 4, 2016
5-4-16
Controlling Operation: Structure Placement
Fraction of day workable 0/10
Hi 55 Lo 43
Weather AM Heavy Rain PM Cloudy light rain windy
Reith Riley had structures delivered. No other work was preformed on this division today due to rain.
Fraction of day workable 0/10
Hi 55 Lo 43
Weather AM Heavy Rain PM Cloudy light rain windy
Reith Riley had structures delivered. No other work was preformed on this division today due to rain.
Tuesday, May 3, 2016
5-3-16
Controlling Operation: Removals
Fraction of day workable 10/10
Hi 69 Lo 48
AM Sunny PM Sunny
Indiana Earth was on site and removed the curb on the the North West corner of Chippewa and Main.
The traffic control needed adjusted at the intersection of Michigan and Chippewa to allow for semi traffic heading north on Michigan heading west on Chippewa to make the corner.
The traffic control needed adjusted at the intersection of Michigan and Chippewa to allow for semi traffic heading north on Michigan heading west on Chippewa to make the corner.
Monday, May 2, 2016
5-2-16
Controlling operation: Removals
Fraction of day workable 10/10
Hi 56 Lo 44
Am Cloudy Light rain Pm Cloudy mist
State Barricade placed the lane restriction on Chippewa from Michigan to just past Main on the North Side. They also closed the west lane of Main between Chippewa and Demour.
Abermash set hubs and grades for phase 1.
Indiana Earth removed curb and sidewalk on the northwest corner of Main and Chippewa.
Rich Estes started overseeing on this Division today.
Fraction of day workable 10/10
Hi 56 Lo 44
Am Cloudy Light rain Pm Cloudy mist
State Barricade placed the lane restriction on Chippewa from Michigan to just past Main on the North Side. They also closed the west lane of Main between Chippewa and Demour.
Abermash set hubs and grades for phase 1.
Indiana Earth removed curb and sidewalk on the northwest corner of Main and Chippewa.
Rich Estes started overseeing on this Division today.
Subscribe to:
Posts (Atom)