Tuesday, May 31, 2016

Friday, May 27, 2016

Thursday, May 26, 2016

5-26-16

Controlling Operation: Phase 2
Fraction of Day Workable: 10/10
Hi 84 Lo 64
Weather AM Cloudy, Humid PM Cloudy, Humid 

No work by the contractor was preformed today.

Turnkey was on site for US Signal, and finished pushing conduit at the intersection of Chippewa and Michigan. Hook-ups are all that is remaining for Turnkey's work in the area.

AEP continued their work relocating their three phase tie at the Chippewa intersection.

5-25-16

Controlling Operation: Phase 2
Fraction of Day Workable: 10/10
Hi 84 Lo 61
Weather AM Sunny PM Partly Cloudy

No work by the contractor was preformed today.

Turnkey was on site for US Signal pushing conduit at the intersection of Chippewa and Michigan.

AEP continued their work relocating their three phase tie at the Chippewa intersection.

Tuesday, May 24, 2016

5-24-16

Controlling Operation: Phase 2
Fraction of day workable 10/10
Hi 85 Lo 60
Am Sunny Pm Sunny

No work by the contractor was preformed today.

Turnkey was on site for US Signal boring at the intersection of Chippewa and Michigan.

Gordon pulled Comcast fiber at the intersection of Chippewa and Michigan.

AEP began work relocating their three phase tie at the Chippewa intersection.

Monday, May 23, 2016

5-23-16

Controlling Operation: Phase 2
Fraction of day workable 10/10
Hi 78 Lo 53
Am Sunny Pm Mostly cloudy Sunny

No work by the contractor was preformed today.

Turnkey was on site for US Signal boring at the intersection of Chippewa and Michigan.

Gordon pulled Comcast fiber at the intersection of Chippewa and Michigan.

Friday, May 20, 2016

5-20-16

No Work Preformed on this Division today

The keys to the Case house was given to Reith Riley.

Thursday, May 19, 2016

Monday, May 16, 2016

5-16-16

Controlling Operation: Phase 2
Fraction of day workable 10/10
Hi 67 Lo 38
Am Mostly Sunny Pm Mostly cloudy

No work by the contractor was preformed today.

Comcast worked on boring on Chippewa running east to west.

Saturday, May 14, 2016

4-22-16

No Work Preformed on this Division today.

5-13-16

No work preformed on this division today.

Meeting Agenda
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
5-13-16


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities


ITEMS TO BE DISCUSSED

The Weeks up Coming Events/Schedule
Division A – Reith Reilly plans to continue preliminary work.  The asbestos testing is expected to be completed by early next week.

Division B – Anticipating the Tuesday closures, Reith Reilly plans to have demolition crews in 3 areas with concrete crews continuing their work on Bartlett.  They plan to begin storm work as early as Tuesday afternoon, immediately following the demolition crews.

Utility Relocation Issues:
                AEP:  Bartlett Street lights have been removed.
           Marion Street: Robert hennery plans on finishing the removal of street lights this                      
Weekend
           Chippewa:
AEP still has not removed their line from the pole at Chippewa, but they plan to start work next week.  Comcast and US Signal were waiting for AEP, but have taken measures to complete their work in spite of AEP’s delays.

                Robert Henry:
Robert Henry will complete their work on the south east corner of Main & Western on Saturday.  They plan to begin work on Marion Street starting next week.  The crossings at Washington, Jefferson, and Western (utilizing a night closure for Western) are expected to be done by June 8.

                NIPSCO/InfraSource
NIPSCO will be done at the Columbia Court area by the morning of the closure on the 17th.  Their work on Main between Madison and Marion was expected to have been completed today, but the water main breakage caused their gas line to fill.  As a result, their work here has been set back a few days and is now expected to be done by the 23rd.  They plan to have all work north of Lassalle done by the 23rd.  There were some concerns about untonable gas lines on Bartlett.  Phil from the utility will have someone go on site to check on these, but he believes the lines have already been shut off and are a nonissue.

                Comcast:
Jay couldn’t make the meeting, but he relayed that Comcast will start work on Chippewa on the 16th and has plans to be out of the area by June 5th.
 The pole on Marion east of Main may need to be held due to its location in reguards to the storm sewer line, since Comcast and AT&T are still on it.

                US Signal:
Charlie O. of the utility has plans to splice beginning June 3rd.  US Signal will be off of the pole and out of the Chippewa intersection by June 5th.

                AT&T:     
No one for AT&T came to the meeting.  I will call Dennis to check up.  The vault on Michigan at Bartlett is preventing Reith Reilly from setting 2 structures.  The line at Marion and Michigan is still scheduled to be moved in the next week.

                Water Dept.
The Water Department discovered two broken valves that need to be fixed as soon as possible without disrupting the construction schedule.  One valve is located on Main Street near the intersection with Lassalle.  The other is located on Lassalle Ave near Main and will require two days to repair.  Ed from South Bend Water has said the work could be completed on a weekend with traffic restricted to one lane and a flagger present.

                 INDOT:
                INDOT was a no show.

Transpo:
Transpo just wanted to confirm the placement of the Temporary Access Lane to the Transpo lot.

Metronet
Metronet has a rigid conduit near Bartlett that may need to be lowered so that Reith Reilly can continue their work in the area.  If the conduit needs lowered Pemberton Davis will do this work, while they are in the area. Some work will also need to be done to determine the fiber line in the handhole location and splicing capabilities.

Stakeholder Questions:
                                Larry with Memorial Hospital inquired about the signage regarding the Michigan Street detours.  Local Traffic Only signs have been added for the south bound traffic north of the river and for the north bound traffic at Lafayette & Marion.  A No Outlet sign will also be added for north bound traffic on Michigan.  Larry will notify EMS of the closures and detour routes.

Additional RW and Encroachments:
                Division A
The Case house will be vacated on the 16th and the City will take ownership of the house on the 20th
Division B
Corbitt will have a resolution for the Burkhart sign this afternoon following today’s meeting.  If Burkhart refuses to remove the sign themselves, a special meeting to call for Condemnation will be held on the 16th to give AEP the legal right to cut the power.  The sign itself can be removed at any time, but likely won’t be down until the 19th or 20th.  The foundation can be removed once the power is taken care of.

Submittals (List at Meeting): No issues with submittals

Action Items
                1 MCI
Quentin, representing MCI, provided drawings detailing the extent of the work MCI has yet to do.  They have a conduit on the northwest corner of Main and South Street that needs to be lowered as soon as possible.  MCI will be placing test holes at other intersections on Main, as well.  MCI also has work to do on the Southwest corner of Main and Washington.  Quentin will relay that this work needs to be started next week.
2 QC/QA HMA
                A change order is being written regarding the QC/QA HMA.
                3 Redesign on Mich/Marion
The structures on Michigan west side between Madison and Lasalle may need to be altered to tie into the existing structure on Lasalle.  Another structure may need to be added at the Michigan and Madison intersection.  The remaining structures between Madison and Marion on Michigan are cast in place.  A meeting has been set with Lawson Fisher on Monday to go over these details.
                4 Chase Tower (Main Street)
There is a vault underneath the Chase Tower that needs to be avoided.  Reith Reilly will need access to do a sawcut and then will avoid sidewalk work and plan to work outside of the problem area.  Tony (Reith Reilly) will review the layout of the curb and get a plan for the construction, working with Leonidas (Chase) to determine how much work can be done.
                5 RFI #4 Permeable Block
                                Division A consists of all non-permeable brick pavers with non-permeable detail.  Division B will have permeable brick pavers for the splitter islands and buffer area.  Reith Reilly is concerned that the special previsions for the non-permeable pavers do not include all of the components of the pay item.  A meeting has been set for Tuesday at the field office with Reith Reilly and the city to work out the details of these concerns.

Reith Riley Construction Concerns/Questions:
                Tony wanted to confirm that loop sealant with no backer rod is being used for the concrete joints on Bartlett.  It was also decided that the signals at the intersection of Michigan and North Shore Drive should be set to red flashers and that the lights should not be bagged for the closure.

City Concerns/Questions:
                               
 Next weekly progress meeting 5-20-15




Thursday, May 12, 2016

5-12-16

Controlling Operation: Concrete
Fraction of day workable 6/8
Hi 76 Lo 62
Weather AM Partly Cloudy PM Cloudy Rain

Reith Riley placed backfill around the curbs at Chippewa and Main St North west corner.

Had a meeting with today with AEP, Comcast, Reith Riley and Lawson Fisher on site to review the condition of the utilities relocation's. Everyone claims they will be done by June 5th.

Wednesday, May 11, 2016

5-11-16

Controlling Operation: Cub and Gutter
Fraction of day workable 8/8
Hi 76 Lo 56
Weather Am Partly Cloudy Pm Partly Cloudy

Reith Riley finished pouring the curb on Phase 1. Once the curb was poured it was apparent the grade change will be an issue during construction.

Tuesday, May 10, 2016

5-10-16

Controlling operation: concrete curb and gutter
Fraction of day workable 0/8
Hi 65 Lo 48
Weather Am Rain PM Rain

No work preformed today due to rain.

Monday, May 9, 2016

5-9-16

Controlling Operation: Curb and Gutter Placement
fraction of day workable 8/8
Hi 58 Lo 45
Weather Am Light Rain PM cloudy Mist

Reith Riley placed forms and poured the curb and gutter at Chippewa and Main.

I talked with Charlie O. of US Signal to get the cable on Chippewa started. he still needs permits from the City.

Saturday, May 7, 2016

5-7-16

No work on this division today.

5-6-15

Controlling operation: Structure placement.
Fraction of day Workable 10/10
Hi 76 Lo 48
Weather AM Sunny PM Sunny

Reith Riley rebuilt the structure on the corner of Chippewa and Main and backfilled the pipe structures at this intersection.



The weekly progress meeting was held today. See min. below.

Meeting Minutes
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
5-6-16


Regarding:
Project 116-001 Two Way Conversion Weekly Progress Meeting

Construction and Utilities


ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
Reith Riley plans on finishing up Division A Phase 1.
They are going to Demo Mar Main Pharmacy.  They will work on sidewalk and approaches on Bartlett east of Michigan. West of Michigan on Bartlett they will work on concrete paving and subgrade work. They also plan on doing water main work on Main St. just south of Marion

Utility Relocation Issues:
                AEP: 
  The light North of Bartlett on the east side will be taken down next week.  25 lights will be taken down late next week at the intersection on Michigan and Marion and Main and Marion
                   Tony from Reith Riley will be getting with Fran from AEP to go over the down town area on light removals.
   Tony Macia with AEP has not started the relocation work on Chippewa yet. He said they should be next week and be finished by the last week of May.
                Robert Henry:
                    Robert hennery is done by the Library and are continuing South. They plan on closing Washington on the 16th or 17th. They are still ahead of schedule.
                NIPSCO/InfraSource
                     Lassalle Ave work is completed. They are having trouble going down the Columbia Court Area due to a lot of abandoned foundations. They are going to have to open cut across main at Colfax due to all the vaults in the intersection. This work will have to be completed by the 16th. They will be doing 2 lanes at a time. All work will be completed on Lafayette St. by the 16th of May all travel lanes and parking lanes will be free from work and open to traffic. Toy will be checking on the work that HRP is doing on Lafayette to help to get the lanes opened up for the 17th closure of Marion and Bartlett.            
                Comcast:
                       No one showed up for Comcast. I will call and get an update.

                US Signal:
                       No one showed up. I called Charlie and they still don’t have their permits.
                      

                AT&T:          
                     No one for AT@T came to the meeting.
                     Bartlett Street Ally East of Michigan the pole is still in the way and was supposed to be removed Monday. The vault at Michigan and Bartlett will begin on Monday. The line at Marion and Michigan is scheduled to be moved in the next 2 weeks.

                Water Dept. was a no show

                 INDOT: was a no show

 Transpo was wanting an intersection schedule. I will get that to them. They also wanted to make sure the drive construction on South St. will not affect pickups. Transpo has a bus that parks on South St. to do pickups, which could be affected during construction.

              Metronet needs notified to do the work at the South East corner Bartlett and Michigan to the handhole.

Stakeholder; I notified Larry Lies of Memorial that the cross walk at Bartlett and Michigan may be lost due to the work that AT@T is doing at the intersection may affect the wiring to the traffic signal. Toy is going to contact the Chase Tower when work starts up in the area to have the barrier wall moved and to have the window installation stopped when Reith Riley is working in the area. A sleeve will need to be placed for electric for signs placed later by the hospital.

10:00 am 10:10 Break Utility and Stakeholders can leave

Additional RW and Encroachments:
                Division A
1.       Sandra V Case: will move out on the 17th can do asbestos check on the 18th.
                Division B
1.       Fifth Third bank: should not be an issue
2.       Burkhart sign: Reith Riley needs to know before the 17th if they are doing the work or if Burkhart is going to have the sign removed before the 17th.

Submittals (List at Meeting): no issues with submittals

Action Items
                                1 QC/QA concrete: This will be a no cost change order.
                                2 QC/QA HMA : Reith Riley is still working on a price.
                                3 Mar Main Demo : The gas still needs disconnected so the demo work can be done. This temporary road can’t be built with Mar Main still standing.
                                4 Chase Tower (Main Street):
                                5 RFI #4 Permeable Block: Reith Riley should receive the reply by the end of the day.

Reith Riley Construction Concerns/Questions:

City Concerns/Questions:
                               
 Next weekly progress meeting 5-13-15






Thursday, May 5, 2016

5-5-16

Controlling Operation: Structure Placement
Fraction of day workable 10/10
Hi 64 Lo 45
Weather AM Sunny PM Sunny

Reith Riley had a crew placing pipe pipe on the North West Corner of Main and Chippewa. While placing pipe a AT&T line was struck. Two lines inside the cable where severed. AT&T will be onsite for repairs tomorrow. 



The South Bend Water deptment delivered a casting to replace an existing manhole lid that was broken. The casting was broken prior to any work preformed at this site. 
  

Wednesday, May 4, 2016

5-4-16

Controlling Operation: Structure Placement
Fraction of day workable 0/10
Hi 55 Lo 43
Weather AM Heavy Rain PM Cloudy light rain windy

Reith Riley had structures delivered. No other work was preformed on this division today due to rain.

Tuesday, May 3, 2016

5-3-16

Controlling Operation: Removals
Fraction of day workable 10/10
Hi 69 Lo 48
AM Sunny PM Sunny

Indiana Earth was on site and removed the curb on the the North West corner of Chippewa and Main.

The traffic control needed adjusted at the intersection of Michigan and Chippewa to allow for semi traffic heading north on Michigan heading west on Chippewa to make the corner.



Monday, May 2, 2016

5-2-16

Controlling operation: Removals
Fraction of day workable 10/10


Hi 56 Lo 44
Am Cloudy Light rain Pm Cloudy mist

State Barricade placed the lane restriction on Chippewa from Michigan to just past Main on the North Side. They also closed the west lane of Main between Chippewa and Demour.

Abermash  set hubs and grades for phase 1.

Indiana Earth removed curb and sidewalk on the northwest corner of Main and Chippewa.

Rich Estes started overseeing on this Division today.