Thursday, May 5, 2016

5-5-16

Controlling Operation: Structure Placement
Fraction of day workable 10/10
Hi 64 Lo 45
Weather AM Sunny PM Sunny

Reith Riley had a crew placing pipe pipe on the North West Corner of Main and Chippewa. While placing pipe a AT&T line was struck. Two lines inside the cable where severed. AT&T will be onsite for repairs tomorrow. 



The South Bend Water deptment delivered a casting to replace an existing manhole lid that was broken. The casting was broken prior to any work preformed at this site. 
  