Thursday, May 12, 2016

5-12-16

Controlling Operation: Concrete
Fraction of day workable 6/8
Hi 76 Lo 62
Weather AM Partly Cloudy PM Cloudy Rain

Reith Riley placed backfill around the curbs at Chippewa and Main St North west corner.

Had a meeting with today with AEP, Comcast, Reith Riley and Lawson Fisher on site to review the condition of the utilities relocation's. Everyone claims they will be done by June 5th.