Fraction of Day workable 10/10
AM Partly Cloudy PM Cloudy
Hi 64 Lo 48
Wisco was on site working on the North East corner of Chippewa and Main.
Air Marking was on site and did Park street between Michigan and Main.
No other work took place on this project today.
Meeting Agenda
Meeting With:
|
|
|
|
Meeting Date:
|
|
|
|
Regarding:
|
|
|
Construction and
Utilities
|
|
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
1.
Traffic Closure Updates
A.
Bronson and South Street: South Street opened
yesterday and Bronson Street will remain closed to the east of Main until
November 15th.
B.
Colfax/Jefferson/Washington/Wayne: side streets
will see minor delays only when work takes place on the corners. Washington
will close in 2 weeks when woodruff is back in to do the structure at
Washington and Main.
C. Saint Joe: Saint Joe will remain 1 lane
until November 15th and the side streets will see
delays of 20min while concrete curb is being poured next week.
C.
Michigan and Main will open today from Sample to
Ewing and Main Street will open tomorrow from Sample to Marion for two-way
traffic.
Utility Relocation Issues:
AEP:
Robert Henry: Robert Henry
and AEP will be redoing the schedule for Michigan Street from Washington to
Western. They will work from the North to the South. Trying to work on
Washington while it is closed with JMS. The intersection of Monroe and Main
will need to be worked on that time is yet to be determined.
NIPSCO/InfraSource:
Comcast:
AT&T: The Main hole
in the parking Stall between Colfax and Washington was determined to be an old
Steam vault. The casting will be removed and the vault filled in with flowfill.
Water Dept: The water department needs to adjust some
valves at the intersection Jefferson Wayne and LaSalle on Saint Joe. A meeting
on sight Monday will be held to review the
traffic control. The water dept. would also like a no left turn be placed at
the office at Colfax and Main St. Drive up window.
Transpo: Wants to make sure
the timings on the signals at South and Bronson on Michigan is being addressed.
Metronet: No issues
Utilities Q/A
INDOT: Questions: Did not attend
Stakeholder
Questions: Larry would like the block moved from in front of the door to
the building that sets on Madison east of Michigan.
Chase tower concerned over getting between cub and building
to remove canopy and brick face.
311 wanted to confirm street name signs being placed back at
Michigan and Broadway
10:00 am 10:10 Break Utility
and Stakeholders can leave
Action Items
1
Upcoming work for the week: continue to work on
the crossings and cycle track on Main Street. Start prepping for blocks and
pavers between the curb and cycle track. Continue to work on the traffic and
street lighting on Main Street. Pour curb on Saint Joe. Start milling and
paving on the 24th on Michigan from LaSalle working north. Finish up
the cross walks and side walk at Chippewa.
2
Cross Walks/completed on Main: Reith riley will
try to complete the cross walk on Main Street and they Maintain cross walks on
Saint Joe.
3
Signs/ status/speed limit Change order:
Pemberton davis will remove signage and place new signs on the opened portions
as quickly as possible.
4
Light pole footer claim /change order: The
claim will be reviewed and responded to in writing at the first of next week.
No penalties will be enforced due to the lighting not being completed as long
as Pemberton Davis continues to work on it and it is completed as soon as possible.
5
Oct. 15 expectations and penalties: Stop
bars, turn arrows, lane lines, Cross walks and traffic signals on Main St. with
the exception of Bronson are all up and functioning. No penalties will be
enforced on Main Street obligations have been met.
6
Strain Poles and cabinets due in: Division
A is expecting the Cabinets in around November 1. Division B Pemberton Davis is
expecting the Strain poles and cabinets in the second week of November. A
meeting will take place one day next week to look at the constructability of
the LaSalle and Michigan Corner and keep traffic signals working. I will
forward on a signed copy of the change order to Reith Riley and Martell.
7
Next meeting every other week: The next
Progress Meeting will be held in two weeks on a trial bases.
Reith Riley Construction
Concerns/Questions:
Reith riley would like to get portions of the contract
substantially complete before winter and give them back to the City.
City
Concerns/Questions:
Need to look at the ped head at Main and Ewing pole appears
in the way.
Make sure stripping on side streets is placed correctly
(Jefferson is incorrect)
Next weekly progress meeting 10-28-16
No comments:
Post a Comment