10-25-16

Controlling Operation: Traffic Markings
Fraction of Day workable 10/10
AM Mostly Sunny PM Sunny 
Hi 58 Lo 37

reith Riley had a crew pour the ramp and sidewalk on the North west corner of Michigan and Chippewa.

Acorn placed the sod at Palmer, north east corner of Michigan and Chippewa.

No other work took place today.