Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Mostly Sunny PM Mostly Sunny
Hi 75 Lo 55
Ziolkowski continued to place the brick veneer on the concrete walls in the Chippewa roundabout.
Rieth-Riley had a concrete crew that poured the lower apron in the roundabout and graded the upper apron. They also formed sidewalk and the splitter island at the intersection of Main and Chippewa.
Air Markings was on site water blasting the concrete pavement.
Martell was installing light foundations and running conduit to those foundations on the north side of Chippewa between Main and Michigan.