Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 88 Lo 75
Ziolkowski was installing the wall caps and planters on the roundabout walls in the center of the Chippewa roundabout.
Martell was installing signage at the Chippewa roundabout and the detector housing at the intersection of Main and Chippewa.
AirMarkings finished striping Main and Michigan south of Ewing and also striped Barbie.
Rieth-Riley poured the splitter island at the intersection of Main and Chippewa and also poured the upper apron of the roundabout.