Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Partly Cloudy PM Partly Cloudy
Hi 73 Lo 58
Rieth-Riley had a curb crew that finished the curb on Chippewa east of Main. They also placed the top curb ban and 1/2 of the second ban of the curb.
Ziolkowski began placing the brick veneer on the Chippewa roundabout walls.
Reith Rileys prep crew finished backfilling inside the Chippewa roundabout walls and worked on cleaning up.
Martell worked on light pole foundations on chippewa north side west of Michigan and the strain pole on Michigan across from Discount Tire.