Thursday, September 8, 2016

9-8-16

Controlling Operation: Traffic Markings
Fraction of Day workable 0/10
AM Rain  PM Cloudy Light Rain 
Hi 84 Lo 74

Chippewa Round About opened at 11:00 AM

Reith Riley had a Prep crew cleaning the round about area in the AM, They then went and started prepping crosswalks at Don Moyer and Michigan and Ewing and Main Street.

Martell worked on removing old signs and placing new signage from Chippewa to Ewing on Main and Michigan. They also placed left turn arrows at Main and Ewing and main and Chippewa.

State barricade had a 4 man crew working on opening up the round about. Message boards where placed on Main and on Michigan warning of two way Traffic.