Wednesday, August 31, 2016

8-30-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM cloudy Rain  PM Mostly Cloudy
Hi 84 Lo 68

Reith Riley had a paving crew finish paving chippewa and Main Street intersect. They got done by 11:00am

Reith Riley prep crew worked on placing dirt in the round about.

Zoilkowski worked on cleaning up the forms and job site.

Martell worked on street lighting at Chippewa and Michigan South West Quad.