Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Mostly Sunny PM Mostly Sunny
Hi 88 Lo 68
Reith Riley had a crew seal the inside of the Round about. The same crew prepped for the curb in the Cavalry Temple church / North East corner of Main and Chippewa.
Reith Riley had a asphalt crew on site paving surface on Main Street from Chippewa to Farneman Ave.
Martell worked on round about street lighting on the South West quad of Bartlett an Michigan.
Accorn was on site and seeded the South East quad of Michigan and Bartlett.
Zoilkowski worked on removing their forms and cleaning up the job site.