Fraction of Day workable 6/10
AM Mostly Sunny PM Mostly Sunny
Hi 82 Lo 64
Reith Riley had a crew on site and worked on placing structures and pipe on the North Easr corner of Chippewa and Main.
Zoilkowski had a crew on site forming the round about walls.
Martel worked on the intersection of Don Moyer and Michigan and Main and Chippewa.
The city sewer Department came out and camered the pipe on the North East corner of Michigan and Chippewa.
The 12 inch water Main on Chippewa is in conflict with the new storm line Reith Riley will have to get it lowered.
The 12 inch water Main on Chippewa is in conflict with the new storm line Reith Riley will have to get it lowered.