Thursday, August 25, 2016

8-25-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 9/10
AM Early Light Rain, Cloudy  PM Cloudy
Hi 80 Lo 66

Ziolkowski began stripping bracing and formwork off the concrete walls in the center of the Chippewa roundabout.

Rieth-Riley had a curb crew that poured curb at the northeast corner of the Chippewa and Main intersection. They also poured the curb for the island in that section of the intersection. 

Reith Riley prep crew worked on grading the corner of Chippewa and main.

Martell poured the foundation at Chippewa and Main South West corner. They also worked on Don Moyer and Main.