Controlling Operation: Roundabout Wall
Fraction of Day workable 10/10
AM Mostly Sunny PM Mostly Sunny
Hi 76 Lo 56
Rieth-Riley was on site installing an elbow in the water Main on the north side of Chippewa east of Main to allow for the storm pipe to be installed per plan. They then installed the storm pipe to connect structures 62 and 64.
Martell was on site setting the School Zone signs.
Ziolkowski continued setting forms for the concrete walls in the center of the roundabout.
Indiana Earth was on site to excavate the area needed to make the elbow in the water main.