Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Partly cloudy PM cloudy rain late 
Hi 81 Lo 68


Reith Riley had a crew on site backfilling the round about inside the walls to allow for the center pad to set on it.

No other work took place today. 