Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Sunny PM Cloudy
Hi 78 Lo 65
Rieth-Riley had a crew that poured curb on the north side of Chippewa between Michigan and Main. They also poured the approach for the Calvary Temple on Main Street.
Rieth-Riley backfilled inside of the concrete walls at the Chippewa roundabout.
Martell was working on lighting at Chippewa.
Zoilkowski finished cleaning up from the concrete wall pour.