Wednesday, August 31, 2016

8-31-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Sunny  PM Cloudy
Hi 78 Lo 65

Rieth-Riley had a crew that poured curb on the north side of Chippewa between Michigan and Main. They also poured the approach for the Calvary Temple on Main Street. 

Rieth-Riley backfilled inside of the concrete walls at the Chippewa roundabout. 

Martell was working on lighting at Chippewa.

Zoilkowski finished cleaning up from the concrete wall pour.