Fraction of Day workable 7/10
AM Cloudy PM Rain from 12-2, Cloudy
Hi 81 Lo 67
Ziolkowski poured the roundabout walls in the morning and will begin stripping formwork tomorrow.
Fine grading was completed for the island that will be located at the northeast corner of the intersection of Chippewa and Main.
Rieth-Riley had a curb crew that began laying curb at the northeast corner of the intersection of Chippewa and Main.
Martell installed a signal pole at the southeast corner of Michigan and Donmoyer and installed a signal pole foundation at the southwest corner of Main and Chippewa. They also took down the mast arm at the northeast corner of Main and Chippewa.