Fraction of Day workable 10/10
AM Partly cloudy 11 am PM cloudy brief shower
Hi 82 Lo 68
Reith Riley worked on placing pipe at the South East corner of Main and Chippewa. They also worked on grading out along main st.
Zolkowski was on site and forming the walls for the round about.
Indiana earth was on site and do the duck under for the 12 inch main and the storm sewer conflict. They where unable to get the work done due to the water main not shutting down tight. They did not bring pumps along to handle the water.
Martel placed the foundations for the strain poles on the south east and North east corners of Chippewa and Main street.
Meeting Minutes
Martel placed the foundations for the strain poles on the south east and North east corners of Chippewa and Main street.
Meeting With:
|
|
|
|
Meeting Date:
|
|
|
|
Regarding:
|
|
|
Construction and
Utilities
|
|
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
The upcoming week will see lane
restrictions during the day on Main Street and Michigan from Bronson to Sample
for Paving and Milling. Jefferson Street is to be Reopened Monday once the
asphalt is placed.
Utility Relocation Issues:
Robert Henry
Robert Henry
will look at the vault at Marion and Michigan once the meeting is over to
determine how and when to do the work. They will be coordinating with Tony on
the casting adjustments in the parking areas as needed. They will need to do
lane restrictions on Monroe and Main to place a new vault. They will be
completed with the work on LaSalle between Michigan and Main by the end of next
week 8-27-16.
NIPSCO/InfraSource:
Nipsco has the
gas line south of Bronson on Main lowered. They have the untoneable between
Bronson and Sample on Main located. They are working on the gas valve at
Bartlett that is buried under the sidewalk, that work should be complete by
weeks end.
Comcast:
Comcast is looking into lowering the
vault at Chippewa and Michigan North east Corner.
AT&T:
AT& T has a vault in the sidewalk
north of Navarre that Tony is meeting with AT&T to get lowered
Water Dept.:
The water dept, is working on adjusting
castings to grade. They are also assisting in the
12 in.
water main duck under at Chippewa and Main.
Transpo: No Issues
Metronet:
Metronet will be removing the downtown WIFI on Sept 9th if
necessary as Pemberton Davis relocates stop lights that the WIFI is connected
to. Pemberton Davis will be installing a new conduit on the East side of Main
to support future Metronet. Metronet also requested at their expense a new conduit
on the west side of Main from LaSalle to Marion. Metronet needs to get the line
at LaSalle and Main North East corner relocated to the new handhole Pemberton
Davis set.
INDOT: Questions
INDOT questioned the asphalt paving
and coordination with testing. That is happening.
Memorial
The stop sign at
Main and Bartlett had been knocked down. Pemberton Davis will fix it. Larry has
not seen the revised landscape plans with the hospital signs incorporated. He
reminded me of the tree on LaSalle that needs replaced. Larry was also
concerned about pedestrian traffic at Bartlett and Michigan. He would also like
for the cross walk Marion be cleaned.
JMS
JMS will get Main
St back to multiple lanes as soon as they get asphalt base to patch water line
cut. They will have the vault backfilled the first of next week. They need to
make sure they get passing density test.
Marriott
They would like
to use the lane that is closed off for storage until Reith Riley plans to bee
in that area working on Saint Joe. They also would like the light signal
foundation to be removed as soon as possible.
Action Item
1
Palmer down spout drains
It has been determined that the
Palmer down spouts are causing the washout at the Northeast corner of Chippewa
and Michigan. Reith riley will get the vactor truck in and do some more
investigation to determine options. Toy is also going to communicate with
Palmer.
2
Controller Cabinet Change Order
Structure Point is still working
on getting the rest of the information Pemberton Davis needs. Once that
information is obtained Pemberton Davis can get a price and order the material.
The material will have at least a 8 week lead time.
3
Crosswalks on Side Streets
Reith
Riley will try to get the cross walks back in as quickly as possible.
4
Clean up down town area
Reith
riley will be working on clean up in the coming week.
6 Saigon Drive/cutting short
Due to the lack of curb heigth the owners
of Saigon Market are worried about customers cutting the entrance short and
driving into the new fence that is planned. One option suggested was placing a
planter to deter drives. Myron will discuss this with Kevin.
7 Weeds on Bartlett
Reith Riley is aware of the issue and will be addressing it shortly.
Reith Riley Construction
Concerns/Questions:
City
Concerns/Questions:
Street
lighting needs to be activated as soon as possible, due to large areas do not
have any lighting.
The City
wants to have a meeting with Slusser’s prior to placing any trees.
Next weekly progress meeting 8-26-16
No comments:
Post a Comment