Wednesday, August 10, 2016

8-10-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 91 Lo 66

Indiana Earth finished removals at the intersection of Main and Chippewa.

Abonmarche was on site staking the intersection of Main and Chippewa.

Ziolkowski started forming the walls for the center of the Chippewa roundabout.

Martel worked at Ewing and Michigan and Ewing and Main.

No comments: