Thursday, August 11, 2016

8-11-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Cloudy PM Cloudy
Hi 92 Lo 72

Reith Riley has a crew workong on placing the storm structures on the North East corner of Main and Chippewa.     

Zolkouski was on site forming the walls of the round about.

Martel converted the intersection of Main and Ewing to two-way.

Air Marking was on site laying out for striping from Ewing to Sample.


Meeting Minutes
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
8-12-16


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
Michigan road will have lane restrictions north of Bartlett to Angela Boulevard during the resurfacing operations, which should be completed by Wednesday. Main Street will have lane restrictions from Bronson to Sample Monday thru Thursday of next week for resurfacing. Metro Net has completed their work at Jefferson and Main Reith Riley will have the intersection opened by Monday.   


Utility Relocation Issues:

Robert Henry:
     Robert Henry will be working on Main Street between Monroe and South Street on the east side, should be done by next week. They also have work on east Washington that should wrap up next week. Robert Henry will adjust the structure at the North East corner of Michigan and Marion as soon as Reith Riley gets grade stakes set.

NIPSCO/InfraSource:   
     Nipsco is working on lowering the gas line south of Bronson, which should be completed today.
            
Comcast:
     Comcast emailed that they will be contacting Tony for Reith riley about the work on Marion east of Michigan.

Water Dept.: 
     The water Department is working on adjusting castings on Main Street, they are complete from Marion to Wayne. They are going to go down and work from Sample to Bronson next to accommodate Reith Riley’s paving. They are also going to go to Chippewa on Monday and relocate a fire hydrant at the Northeast corner of Main and Chippewa.  The water department requested that the sidewalk in front of the office on Main and Colfax have the sidewalk poured back as soon as possible.

Transpo: Had no issues

Metronet:  
                     Metro Net and the City have an agreement to remove the WIFI for the downtown area. Before removals of the traffic signals, start that the Wi-Fi is connected to Metro Net will need a couple days’ notice. Metro Net also so requested that a new conduit be run from LaSalle to Marion due to the quality of the current conduit.

INDOT: Questions
     INDOT requested an update of the traffic restrictions. The three round-about’s will be open on Sept 7th. Main from LaSalle to Western will be completed by Oct 15th. Saint Joe from Western to LaSalle will be completed Nov 15th.

Stakeholder Questions:
      The new landscape plans were presented to Memorial Hospital. Larry requested that the plans be revised to consider the Hospitals new signage, as to not have the trees block the signs. He had concerns about the public access points to the Hospital when would they be complete. He also had concerns about the traffic control associated with the milling operation between Bartlett and North Shore.

Action Items
     Schedule
           The upcoming week Reith riley will pave from Marion to Angela. They will move down and pave from Bronson to Sample on Wednesday. They will have a concrete crew finishing the sidewalk at the Bartlett street intersection. Then move to the truck apron concrete.  The curb crews will be in and work in the downtown are on Tuesday. Another concrete crew will be working on the cycle track and sidewalk from Marion to LaSalle. Indiana earth will be working on preparing the grade between the sidewalk and the curb in the downtown area on Main Street from Colfax to Wayne. Indian earth will also finish setting grade on Main Street from South Street to Bronson once that is complete Reith Riley will place the subgrade treatment.
 
    1 Work on Saint Joe/ Monroe/ Western
            Pemberton Davis still has traffic signal work to do. Roger requests temporary sidewalks be placed since the sidewalks have been removed for 2 months.
  
    2. Entrance to 5th/ 3rd Bank
             Reith Riley will work on making sure the subs do not block both entrance to the bank.

     3. Strain Pole Change order
              Should be signed and on Toys deck by Monday

     4. Crosswalks on side streets
               Crosswalks on the side streets needs to be kept up for pedestrians. Reith riley will have a                                   crew on Saturday work on some of them.

      5. Work on the East side of Main/ Parking Garages
            Reith Riley and the City will meet on site Monday to go over access and egress from the parking garage at Colfax.




     

                                         
Reith Riley Construction Concerns/Questions:
     
1.       Reith Riley is concerned the overhead structure South of LaSalle will fall into the cycle path. Once it is laid out, the City will have to determine what to do.

2.       The Pave drain mats will leave a void at the header or the curb. The solution is to add another half bock to one side. This will result in the header being reduced by 6 inches.

City Concerns/Questions:
  
The City stressed getting the drives and crosswalks in for pedestrian traffic can flow in the downtown. The lack in activity in the downtown area over the last few weeks has caused the public to become frustrated.                           

 Next weekly progress meeting 8-19-16