Controlling Operation: Roundabout Walls
Fraction of Day workable 10/10
AM Mostly Sunny PM Mostly Sunny
Hi 80 Lo 59
Rieth-Riley had a prep crew grading for the island at the northeast corner of the intersection of Main and Chippewa.
Another Rieth-RIley crew was prepping (milling) the east side of Main north of Chippewa for asphalt.
Martell was on site working on signal poles at the northwest corner of Main and Chippewa.
Zowlkowski worked on forming the walls to the round about, the walls are scheduled to be poured tomorrow.