Wednesday, August 3, 2016

8-3-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Mostly Sunny PM Sunny
Hi 89 Lo 64

Rieth-Riley had a concrete crew that poured the remaining sidewalk in front of the Palmer parking lot. 

Martell was on site pulling wire and setting signal heads at the intersection of Main and Ewing.

KC Trees grinded the stumps of the removed trees at the Case and Palmer lots on the east side of Michigan south of the roundabout.

Ziolkowski continued forming the footings for the roundabout walls. 