Wednesday, August 3, 2016

8-2-16

Controlling Operation:Center of Roundabout
Fraction of Day workable 10/10
AM Mostly Sunny PM Mostly Sunny
Hi 87 Lo 62

Rieth-Riley had a concrete crew pouring sidewalk from the Palmer parking lot and east of the Palmer building. They also poured sidewalk around the southeast corner of the roundabout .

Ziolkowski was forming the footers for the upper retaining walls

WISSCO was on site doing irrigation within the center of the roundabout.

Martell was pulling wire and setting thermal cameras at the intersections of Main and Ewing and Michigan and Ewing. 