Friday, August 26, 2016

8-26-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Mostly Sunny  PM Sunny
Hi 82 Lo 64

Ziolkowski continued stripping forms from the concrete walls in the center of the roundabout. 

Rieth-RIley had an asphalt crew place base at the intersection of Main and Chippewa. 


Reith Rileys preep crew worked on cleaning up the Cavalry Temple Parking lot. 

Martel worked on Wiring the light at Don Moyer and [laced the foundation to the strain pole in front of Discount tire on Michigan.