Tuesday, June 14, 2016

6-13-16

Controlling Operation: Pipe Work
Fraction of Day Workable: 10/10
Hi 85 Lo 63
Weather AM Sunny, PM Mostly Cloudy

Rieth-Riley continued installing storm structures and pipe on Michigan north of Chippewa. There is a water main obstructing the path of the storm pipe connecting structures 48 and 51. It is being determined if the storm pipe can be lowered and run beneath the existing main.

Indiana Earth continued removals on Michigan south of Chippewa.

The sign contractor inspected the Southgate sign.

KC Trees was on site removing trees and clearing island landscaping. 

Martell drilled 6 sign foundation holes for the solar powered signs along Michigan and Main between Chippewa and Ewing.