Controlling Operation: Subgrade Treatment
Fraction of Day Workable: 10/10
Hi 79 Lo 68
Weather AM Cloudy PM Sunny
Rieth-Riley was on site laying borrow and subbase for PCCP. Sub-grade for the concrete pavement is approximately 80% complete.
Martlell was on site cleaning up excess dirt from foundation holes and setting tesco cabinets.