Tuesday, June 14, 2016

6-14-16

Controlling Operation: Pipe Work
Fraction of Day Workable: 9.5/10
Hi 83 Lo 67
Weather AM Cloudy, Rain, PM Cloudy

Rieth-Riley continued setting storm pipe and structures on Chippewa east of Michigan. 

Indiana Earth continued removals of sidewalk and curb & gutter on Michigan south of Chippewa. Indiana Earth did 4 potholes over the MetroNet line prior to removals.

Waterworks shut down the hydrant valve at the northwest corner of the Chippewa/Michigan intersection in the morning.

Martell was on site working on cabinet foundations at Ewing and Donmoyer.