Controlling Operation: Road Closure
Fraction of day workable 10/10
Hi 81 Lo 60
Weather Am Mostly Sunny PM Partly Cloudy brief shower late
Reith Riley closed Chippewa and Michigan road intersection at around 11:00 Am. Reith Riley had a pipe crew forman on site doing layout work.
Air Marking was onsite removing line and painting the detour on Main Street between Sherwood and Chippewa.
State Barricade placed temporary line and temporary tape on Main St. between Chippewa and Barbie St. They also placed all the Barricades for the closure.
martel was on site and moved signal heads and covered signal heads at the intersection of Chippewa and Main. They also worked on removing the signal equipment at the intersection of Michigan and Chippewa.
Met with Ben Holden, Roger, Toy and Tony Macia of AEP to talk about the Strain Pole location and cables at the intersection of Chippewa and Main.