6-15-16

Controlling Operation: Pipe Work
Fraction of Day Workable: 10/10
Hi 89 Lo 66
Weather AM Partly Cloudy, PM Sunny

Indiana Earth continued removals on the north side of Chippewa. Indiana Earth also completed the demolition of the Case on Palmer houses on Michigan.

Rieth-Riely had a crew installing storm pipe and structures. They were able to successfully lower Str. 48 and run piping underneath the existing water main to Str. 78. Concrete was poured at Str. 78 to form a sewer collar for the piping. It was determined that structure 82 was not set at the correct location, after talking with Roger a new structure will be set in the proper location and tied into the miss placed structure at no additional cost.

AT@T has a line and pedestal at the north west corner of Michigan and Chippewa. Denis Bunch came out and he will have a crew next week work on relocating it.

Martell was on site and worked on controller cabinet foundations 