Controlling Operation: PCCP Pavement
Fraction of Day workable 10/10
Hi 73 Lo 48
Weather Am Sunny PM Sunny
Reith riley fine graded for concrete pavement.
Rieth-Riley had a crew excavating and pouring sleeper slabs. A colored concrete test panel was also poured, along with a concrete inlay for truck apron and Type B integral curb for the splitter islands.
Reith Riley also had a crew do a water tap for the irrrigation system in the roundabout.
Met with Ben from Lawson Fisher, Tony, Scott, Pat and Roger to review the layout of the roundabout curb dimensions and the placement of the sign on Michigan south of Bartlett. Wissco was also approved by Roger to repair the irrigation at Palmer and the south west quad of Chippewa.
Met with Bob Kroll on site to review the water valve that falls in the wall footer on the north side of the roundabout. Reith Riley will need a water stop and valve and the valve will be relocated to the west.out from under the footer.