Controlling Operation: Pipe Work
Fraction of Day Workable: 10/10
Hi 77 Lo 57
Weather AM Cloudy, Light Rain PM Cloudy, Light Rain
Indiana Earth continued working on demolishing the two homes on the east side of Michigan south of Chippewa. Both sanitary laterals were capped and backfill work remains.
Rieth-Riley continued setting storm structures and pipe. The pipe run across Michigan was able to be placed under the main. Str. 43 and the corresponding pipe was removed.
Martell was on site digging hand-holes and pole foundations.
Water works delivered 4 valve boxes.