Thursday, June 9, 2016

6-8-16

Controlling Operation: Removals
Fraction of Day Workable: 10/10
Hi 68 Lo 45
Weather AM Partly Cloudy, PM Partly Cloudy


Reith Riley had all the structures delivered. 

Martell removed the 2 remaining signals at the intersection of Chippewa and Michigan and the cabinet at the SE corner of the intersection. Fiber optic line that served O'Brian Park had piggy backed within the cabinet. The disconnection of the cabinet caused O'Brian Park to lose service for several hours while the splice was made. 

Indiana Earth continued removals on Michigan north of Chippewa and Chippewa east of Michigan. They started excavating the splitter island in the intersection and Michigan south of Chippewa.


Additional sidewalk closure signs were placed on Michigan, and more barrels were placed to close off the right turn lane for the northbound Michigan traffic at Barbie. 