Controlling Operation: Sub-grade Treatment
Fraction of Day Workable: 10/10
Hi 77 Lo 57
Weather AM Sunny PM Sunny
Rieth-Riley began laying compacted aggregate for dense subgrade for the roundabout. Reith Riley also hauled in Borrow to get the subgrade up to elevation.
Indiana Earth continued removals on the north side of Chippewa. The approach and sidewalk were removed in front of the Palmer building, along with curb in the Palmer south drive and sidewalk on the south side of Chippewa east of Michigan.
AT@T got the line on the North west corner moved out of the road and behind the side walk.
Dry wells were set in the Palmer Parking Lot.