Controlling Operation: PCCP Pavement
Fraction of Day workable 10/10
Hi 89 Lo 63
Weather Am Mostly Cloudy PM Mostly Sunny

Rieth-Riley had a crew pouring the remaining concrete pavement sections of the south approach and west approach.

The site was graded for asphalt in the sections north and south of the roundabout. 

Rieth-Riley also began forming for curb work which will take place tomorrow (7/12).

Waterworks was on site and capped the 6" line running east-west on Chippewa west of the roundabout. They also cut the 6" main within the island of the roundabout.