Controlling Operation: PCCP Pavement
Fraction of Day workable 10/10
Hi 89 Lo 63
Weather Am Mostly Cloudy PM Mostly Sunny
Rieth-Riley had a crew pouring the remaining concrete pavement sections of the south approach and west approach.
The site was graded for asphalt in the sections north and south of the roundabout.
Rieth-Riley also began forming for curb work which will take place tomorrow (7/12).
Waterworks was on site and capped the 6" line running east-west on Chippewa west of the roundabout. They also cut the 6" main within the island of the roundabout.