Fraction of day workable 10/10
Hi 81 Lo 58
Weather Sunny
Reith Riley had a crew pour the west drive to the Palmer Funeral home on the North side of Chippewa
Reith Riley had asphalt crew place the surface on Michigan north of Chippewa to Ewing starting from the east side working thier way west and stopping on the centerline.
They also had a prep crew working on placing the yard drain on the north side of Chippewa in the Palmer yard.
CE Hughes was on site and milled on Main from Chippewa to Donmoyer. They milled from the east side to the west and left the last 12 foot unmilled to allow traffic to run down that area.
Reith Rily had a second prep crew cleaning up behind the milling operation on Michigan between Ewing and Chippewa.