Wednesday, July 27, 2016

7-26-16

Controlling Operation: Curb
Fraction of Day workable 10/10
AM Overcast PM Sunny
Hi 87 Lo 63

Rieth-Riley had a concrete crew pouring sidewalk and curb ramps on both sides of Michigan south of Chippewa and on the south side of Chippewa west of Michigan.

Another Rieth-Riley crew pour curb and curb and gutter on the south side of CHippewa west of Michigan and at the new curb ramp locations.

Ziolkowski poured the concrete footers for the walls in the center of the Chippewa roundabout.

Wissco was on site spotting irrigation lines.

Martell was on site spotting handholes and signal foundations. 