Controlling Operation: PCCP Pavement
Fraction of Day workable 10/10
Hi 89 Lo 71
Weather Am Mostly Sunny PM Sunny
Rieth-Riley had a concrete crew pouring concrete pavement for the southern half of the east approach of the roundabout.
A second Rieth-Riley crew poured combined curb and gutter on the west side of the south approach.
Indiana Earth had a two-man crew that finished removals at the intersection of Michigan and Donmoyer.
Waterworks capped the main east of Michigan on Chippewa in front of the Palmer building. They ran new service line to the meter pit from the West cap of the 6" main on Chippewa.