Tuesday, July 5, 2016

7-5-16

Controlling Operation: PCCP Pavement
Fraction of Day workable 10/10
Hi 80 Lo 64
Weather Am Mostly Cloudy PM Mostly Cloudy

Rieth-Riley had a concrete crew pouring concrete pavement for the Chippewa roundabout they poured the outer circle on the East half. They also formed the west approach to the roundabout and graded the drives for Palmer and 3710 Michigan St. They also cut grade along the Cavalry temple church for the new curb

Indiana Earth had a 2 man crew removing curb and sidewalk at the intersections of Donmoyer and Michigan and Main and Ewing.