7-19-16

Controlling Operation: Curb
Fraction of Day workable 10/10
Hi 88 Lo 71
Weather Am Mostly Sunny PM Sunny, HOT

CE Hughes crew  milled the west side of Michigan between Chippewa and Ewing and Michigan south of Chippewa . They also milled Main St. between Ewing and Farneman. 

Rieth-Riley had a concrete crew that poured drives for the homes on Michigan south of Chippewa and the sidewalk on the east side of Michigan south of Chippewa. They also poured curb ramps for the west, east, and north roundabout splitter islands.  

The prep crew worked on grading for side walk and drives on the north west quad of Chippewa and Michigan.