Controlling Operation: Curb
Fraction of Day workable 10/10
Hi 89 Lo 64
Weather Am Mostly Sunny PM Sunny, HOT
Rieth-Riley had two concrete crews, a curb crew, and an asphalt crew on site today. The concrete crews poured Palmer approaches and sidewalk adjacent to Palmer and at the northeast corner of the roundabout. The curb crew poured integral curb all along the roundabout and on the south and west splitter islands.
The asphalt crew paved Michigan St. south of Chippewa, Main St. between Ewing and Farneman, and Michigan between Chippewa and Ewing.