Saturday, July 9, 2016

7-9-16

Controlling operation:concrete pavement
Fraction of day workable 10/10
Hi 72 Low 63
Weather AM Mostly sunny PM Mostly Sunny

Reith Riley had a concrete crew pour the inside south bound lane of the of Michigan, Then they poured the eastbound outside lane west of the roundabout. they then poured the north bound outside lane south of the round about.

Reith Riley also had a crew placing curb. They started north of the round about east side then west side. They then move south of the roundabout and poured the west side then the east side.

They also had a prep crew on site working on breaking up the footer to the old moument setting in the old island.