Thursday, July 28, 2016

7-28-16

Controling Operation Round about wall
Fraction of day workable 10/10
Weather AM Sunny PM Cloudy Shower
Hi 89 Lo 68

Ziolkowski was not on site today.

Acorn hauled in black dirt and prepped for sod.

Reith Riley had a concrete crew forming and pouring sidewalk and miscilaniace pieces of curb.

Reith Riley had a prep crew working on digging out the upper level footers for the roundabout walls.

Martell worked on the signal at Michigan and Ewing and Michigan and Don Moyer.