Wednesday, August 31, 2016

8-30-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM cloudy Rain  PM Mostly Cloudy
Hi 84 Lo 68

Reith Riley had a paving crew finish paving chippewa and Main Street intersect. They got done by 11:00am

Reith Riley prep crew worked on placing dirt in the round about.

Zoilkowski worked on cleaning up the forms and job site.

Martell worked on street lighting at Chippewa and Michigan South West Quad.

8-29-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Mostly Sunny  PM Mostly Sunny
Hi 88 Lo 68

Reith Riley had a crew seal the inside of the Round about. The same crew prepped for the curb in the Cavalry Temple church / North East corner of Main and Chippewa.

Reith Riley had a asphalt crew on site paving surface on Main Street from Chippewa to Farneman Ave. 

Martell worked on round about street lighting on the South West quad of Bartlett an Michigan.

Accorn was on site and seeded the South East quad of Michigan and Bartlett.

Zoilkowski worked on removing their forms and cleaning up the job site.

8-31-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Sunny  PM Cloudy
Hi 78 Lo 65

Rieth-Riley had a crew that poured curb on the north side of Chippewa between Michigan and Main. They also poured the approach for the Calvary Temple on Main Street. 

Rieth-Riley backfilled inside of the concrete walls at the Chippewa roundabout. 

Martell was working on lighting at Chippewa.

Zoilkowski finished cleaning up from the concrete wall pour.

Saturday, August 27, 2016

8-27-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM rain Sunny  PM Rain
Hi 82 Lo 64

Rieth Riley had a prep crew on site working on grading out for the curb to the Cavalry Temple Church parking lot.

Martell was on site to work on street lighting. 

Rain moved in at 8 am and work was suspended for the day.

Friday, August 26, 2016

8-26-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Mostly Sunny  PM Sunny
Hi 82 Lo 64

Ziolkowski continued stripping forms from the concrete walls in the center of the roundabout. 

Rieth-RIley had an asphalt crew place base at the intersection of Main and Chippewa. 


Reith Rileys preep crew worked on cleaning up the Cavalry Temple Parking lot. 

Martel worked on Wiring the light at Don Moyer and [laced the foundation to the strain pole in front of Discount tire on Michigan.

Thursday, August 25, 2016

8-25-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 9/10
AM Early Light Rain, Cloudy  PM Cloudy
Hi 80 Lo 66

Ziolkowski began stripping bracing and formwork off the concrete walls in the center of the Chippewa roundabout.

Rieth-Riley had a curb crew that poured curb at the northeast corner of the Chippewa and Main intersection. They also poured the curb for the island in that section of the intersection. 

Reith Riley prep crew worked on grading the corner of Chippewa and main.

Martell poured the foundation at Chippewa and Main South West corner. They also worked on Don Moyer and Main.






Wednesday, August 24, 2016

8-24-16

Controlling Operation LaSalle to Ewing: Curb
Fraction of Day workable 7/10
AM Cloudy  PM Rain from 12-2, Cloudy
Hi 81 Lo 67

Ziolkowski poured the roundabout walls in the morning and will begin stripping formwork tomorrow.

Fine grading was completed for the island that will be located at the northeast corner of the intersection of Chippewa and Main. 

Rieth-Riley had a curb crew that began laying curb at the northeast corner of the intersection of Chippewa and Main. 

Martell installed a signal pole at the southeast corner of Michigan and Donmoyer and installed a signal pole foundation at the southwest corner of Main and Chippewa. They also took down the mast arm at the northeast corner of Main and Chippewa. 


Tuesday, August 23, 2016

8-23-16

Controlling Operation: Roundabout Walls
Fraction of Day workable 10/10
AM Mostly Sunny  PM Mostly Sunny
Hi 80 Lo 59

Rieth-Riley had a prep crew grading for the island at the northeast corner of the intersection of Main and Chippewa. 

Another Rieth-RIley crew was prepping (milling) the east side of Main north of Chippewa for asphalt.

Martell was on site working on signal poles at the northwest corner of Main and Chippewa.

Zowlkowski worked on forming the walls to the round about, the walls are scheduled to be poured tomorrow.

Monday, August 22, 2016

8-22-16

Controlling Operation: Roundabout Wall
Fraction of Day workable 10/10
AM Mostly Sunny  PM Mostly Sunny
Hi 76 Lo 56

Rieth-Riley was on site installing an elbow in the water Main on the north side of Chippewa east of Main to allow for the storm pipe to be installed per plan. They then installed the storm pipe to connect structures 62 and 64.

Martell was on site setting the School Zone signs.

Ziolkowski continued setting forms for the concrete walls in the center of the roundabout. 

Indiana Earth was on site to excavate the area needed to make the elbow in the water main.


Saturday, August 20, 2016

8-20-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Partly cloudy PM cloudy rain late 
Hi 81 Lo 68


Reith Riley had a crew on site backfilling the round about inside the walls to allow for the center pad to set on it.

No other work took place today. 

Friday, August 19, 2016

8-19-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Partly cloudy 11 am PM cloudy brief shower  
Hi 82 Lo 68

Reith Riley worked on placing pipe at the South East corner of Main and Chippewa. They also worked on grading out along main st.

Zolkowski was on site and forming the walls for the round about.

Indiana earth was on site and do the duck under for the 12 inch main and the storm sewer conflict. They where unable to get the work done due to the water main not shutting down tight. They did not bring pumps along to handle the water.

Martel placed the foundations for the strain poles on the south east and North east corners of Chippewa and Main street.


Meeting Minutes
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
8-19-16


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
     The upcoming week will see lane restrictions during the day on Main Street and Michigan from Bronson to Sample for Paving and Milling. Jefferson Street is to be Reopened Monday once the asphalt is placed.


Utility Relocation Issues:
Robert Henry
                                Robert Henry will look at the vault at Marion and Michigan once the meeting is over to determine how and when to do the work. They will be coordinating with Tony on the casting adjustments in the parking areas as needed. They will need to do lane restrictions on Monroe and Main to place a new vault. They will be completed with the work on LaSalle between Michigan and Main by the end of next week 8-27-16.
NIPSCO/InfraSource:   
                Nipsco has the gas line south of Bronson on Main lowered. They have the untoneable between Bronson and Sample on Main located. They are working on the gas valve at Bartlett that is buried under the sidewalk, that work should be complete by weeks end.

Comcast: 
      Comcast is looking into lowering the vault at Chippewa and Michigan North east Corner.

                AT&T: 
                      AT& T has a vault in the sidewalk north of Navarre that Tony is meeting with AT&T to get lowered

Water Dept.: 
                      The water dept, is working on adjusting castings to grade. They are also assisting in the
                12 in. water main duck under at Chippewa and Main.

Transpo:  No Issues

Metronet:    
     Metronet will be removing the downtown WIFI on Sept 9th if necessary as Pemberton Davis relocates stop lights that the WIFI is connected to. Pemberton Davis will be installing a new conduit on the East side of Main to support future Metronet. Metronet also requested at their expense a new conduit on the west side of Main from LaSalle to Marion. Metronet needs to get the line at LaSalle and Main North East corner relocated to the new handhole Pemberton Davis set.

INDOT: Questions
     INDOT questioned the asphalt paving and coordination with testing. That is happening.

Memorial
      The stop sign at Main and Bartlett had been knocked down. Pemberton Davis will fix it. Larry has not seen the revised landscape plans with the hospital signs incorporated. He reminded me of the tree on LaSalle that needs replaced. Larry was also concerned about pedestrian traffic at Bartlett and Michigan. He would also like for the cross walk Marion be cleaned.

JMS
     JMS will get Main St back to multiple lanes as soon as they get asphalt base to patch water line cut. They will have the vault backfilled the first of next week. They need to make sure they get passing density test.

Marriott
       They would like to use the lane that is closed off for storage until Reith Riley plans to bee in that area working on Saint Joe. They also would like the light signal foundation to be removed as soon as possible.

Action Item
1           Palmer down spout drains
It has been determined that the Palmer down spouts are causing the washout at the Northeast corner of Chippewa and Michigan. Reith riley will get the vactor truck in and do some more investigation to determine options. Toy is also going to communicate with Palmer.

2           Controller Cabinet Change Order
Structure Point is still working on getting the rest of the information Pemberton Davis needs. Once that information is obtained Pemberton Davis can get a price and order the material. The material will have at least a 8 week lead time.

3           Crosswalks on Side Streets
Reith Riley will try to get the cross walks back in as quickly as possible.

4           Clean up down town area
Reith riley will be working on clean up in the coming week.

6      Saigon Drive/cutting short
                      Due to the lack of curb heigth the owners of Saigon Market are worried about customers cutting the entrance short and driving into the new fence that is planned. One option suggested was placing a planter to deter drives. Myron will discuss this with Kevin.
               
7      Weeds on Bartlett
        Reith Riley is aware of the issue and will be addressing it shortly.
                                         
Reith Riley Construction Concerns/Questions:

City Concerns/Questions:
           Street lighting needs to be activated as soon as possible, due to large areas do not have any lighting.
            The City wants to have a meeting with Slusser’s prior to placing any trees.
           
                               
 Next weekly progress meeting 8-26-16



Thursday, August 18, 2016

8-18-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 6/10
AM cloudy rain 11 am PM Partly Sunny 
Hi 82 Lo 64

Reith Riley worked on placing pipe at the South East corner of Main and Chippewa.

Zolkowski was on site and formed the walls for the round about.

Indiana earth was suppose to be on site and do the duck under for the 12 inch main and the storm sewer conflict.

Wednesday, August 17, 2016

8-17-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 6/10
AM Mostly Sunny PM Mostly Sunny 
Hi 82 Lo 64

Reith Riley had a crew on site and worked on placing structures and pipe on the North Easr corner of Chippewa and Main.

Zoilkowski had a crew on site forming the round about walls.

 Martel worked on the intersection of Don Moyer and Michigan and Main and Chippewa.

The city sewer Department came out and camered the pipe on the North East corner of Michigan and Chippewa.

The 12 inch water Main on Chippewa is in conflict with the new storm line Reith Riley will have to get it lowered.

Tuesday, August 16, 2016

8-16-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 6/10
AM Cloudy rain PM Cloudy Rain 
Hi 82 Lo 64

No work was preformed today due to the rain overnight, 5 to 8 inches of rain happened overnight.

Saturday, August 13, 2016

8-13-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 8/10
AM Cloudy Rain PM Cloudy Rain 
Hi 82 Lo 72

Reith Riley had a crew placing pipe and dry well on the North east corner of Main and Chippewa. 

No other work took place today.

Friday, August 12, 2016

8-12-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Cloudy PM CloudyRain after 3:00PM
Hi 92 Lo 72

Reith Riley has a crew workong on placing the storm structures on the North East corner of Main and Chippewa.     

Zolkouski was on site forming the walls of the round about.

Martel worked at the intersection of Michigan and Ewing and Michigan and DonMoyer.

Air Marking was on site laying out for striping from Ewing to Sample.

Thursday, August 11, 2016

8-11-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Cloudy PM Cloudy
Hi 92 Lo 72

Reith Riley has a crew workong on placing the storm structures on the North East corner of Main and Chippewa.     

Zolkouski was on site forming the walls of the round about.

Martel converted the intersection of Main and Ewing to two-way.

Air Marking was on site laying out for striping from Ewing to Sample.


Meeting Minutes
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
8-12-16


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
Michigan road will have lane restrictions north of Bartlett to Angela Boulevard during the resurfacing operations, which should be completed by Wednesday. Main Street will have lane restrictions from Bronson to Sample Monday thru Thursday of next week for resurfacing. Metro Net has completed their work at Jefferson and Main Reith Riley will have the intersection opened by Monday.   


Utility Relocation Issues:

Robert Henry:
     Robert Henry will be working on Main Street between Monroe and South Street on the east side, should be done by next week. They also have work on east Washington that should wrap up next week. Robert Henry will adjust the structure at the North East corner of Michigan and Marion as soon as Reith Riley gets grade stakes set.

NIPSCO/InfraSource:   
     Nipsco is working on lowering the gas line south of Bronson, which should be completed today.
            
Comcast:
     Comcast emailed that they will be contacting Tony for Reith riley about the work on Marion east of Michigan.

Water Dept.: 
     The water Department is working on adjusting castings on Main Street, they are complete from Marion to Wayne. They are going to go down and work from Sample to Bronson next to accommodate Reith Riley’s paving. They are also going to go to Chippewa on Monday and relocate a fire hydrant at the Northeast corner of Main and Chippewa.  The water department requested that the sidewalk in front of the office on Main and Colfax have the sidewalk poured back as soon as possible.

Transpo: Had no issues

Metronet:  
                     Metro Net and the City have an agreement to remove the WIFI for the downtown area. Before removals of the traffic signals, start that the Wi-Fi is connected to Metro Net will need a couple days’ notice. Metro Net also so requested that a new conduit be run from LaSalle to Marion due to the quality of the current conduit.

INDOT: Questions
     INDOT requested an update of the traffic restrictions. The three round-about’s will be open on Sept 7th. Main from LaSalle to Western will be completed by Oct 15th. Saint Joe from Western to LaSalle will be completed Nov 15th.

Stakeholder Questions:
      The new landscape plans were presented to Memorial Hospital. Larry requested that the plans be revised to consider the Hospitals new signage, as to not have the trees block the signs. He had concerns about the public access points to the Hospital when would they be complete. He also had concerns about the traffic control associated with the milling operation between Bartlett and North Shore.

Action Items
     Schedule
           The upcoming week Reith riley will pave from Marion to Angela. They will move down and pave from Bronson to Sample on Wednesday. They will have a concrete crew finishing the sidewalk at the Bartlett street intersection. Then move to the truck apron concrete.  The curb crews will be in and work in the downtown are on Tuesday. Another concrete crew will be working on the cycle track and sidewalk from Marion to LaSalle. Indiana earth will be working on preparing the grade between the sidewalk and the curb in the downtown area on Main Street from Colfax to Wayne. Indian earth will also finish setting grade on Main Street from South Street to Bronson once that is complete Reith Riley will place the subgrade treatment.
 
    1 Work on Saint Joe/ Monroe/ Western
            Pemberton Davis still has traffic signal work to do. Roger requests temporary sidewalks be placed since the sidewalks have been removed for 2 months.
  
    2. Entrance to 5th/ 3rd Bank
             Reith Riley will work on making sure the subs do not block both entrance to the bank.

     3. Strain Pole Change order
              Should be signed and on Toys deck by Monday

     4. Crosswalks on side streets
               Crosswalks on the side streets needs to be kept up for pedestrians. Reith riley will have a                                   crew on Saturday work on some of them.

      5. Work on the East side of Main/ Parking Garages
            Reith Riley and the City will meet on site Monday to go over access and egress from the parking garage at Colfax.




     

                                         
Reith Riley Construction Concerns/Questions:
     
1.       Reith Riley is concerned the overhead structure South of LaSalle will fall into the cycle path. Once it is laid out, the City will have to determine what to do.

2.       The Pave drain mats will leave a void at the header or the curb. The solution is to add another half bock to one side. This will result in the header being reduced by 6 inches.

City Concerns/Questions:
  
The City stressed getting the drives and crosswalks in for pedestrian traffic can flow in the downtown. The lack in activity in the downtown area over the last few weeks has caused the public to become frustrated.                           

 Next weekly progress meeting 8-19-16



Wednesday, August 10, 2016

8-10-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 91 Lo 66

Indiana Earth finished removals at the intersection of Main and Chippewa.

Abonmarche was on site staking the intersection of Main and Chippewa.

Ziolkowski started forming the walls for the center of the Chippewa roundabout.

Martel worked at Ewing and Michigan and Ewing and Main.

Tuesday, August 9, 2016

8-9-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 88 Lo 60

Indiana Earth was doing removals at the northeast corner of the intersection of Main and Chippewa.

Martell was pouring pedestal foundations at the intersections of Michigan and Donmoyer and Michigan and Ewing. 

Directional Drillers was on site finishing the directional bores at the intersection of Main and Ewing. 

Monday, August 8, 2016

8-8-16

Controlling Operation: Center of Roundabout
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 85 Lo 62

Martell was on site placing lighting foundations at Chippewa.

Rieth-Riley had a crew pouring curbs and sidewalks at the intersections of Michigan and Donmoyer and Michigan and Ewing. They also repoured the colored crosswalk that crosses Michigan south of Chippewa.